Skip navigation | Accessibility and accesskey details | Sitemap

National Audit Office Press Notice

PFI: Construction Performance

THIS STATEMENT IS NOT FOR PUBLICATION OR BROADCAST BEFORE 00.01 HOURS ON WEDNESDAY 5 FEBRUARY 2003

Report by the Comptroller and Auditor General
HC 371 2002-2003
5 February 2003
ISBN: 0102920141
Price: £7.25

Most construction work under the Private Finance Initiative (PFI) is being delivered on time and at the cost expected by the public sector. Central government has generally obtained a much higher degree of price certainty and timely delivery of good quality built assets, compared to previous conventional government building projects, Sir John Bourn, Head of the National Audit Office, reported to Parliament today.

Data produced by the NAO, the first independent analysis of construction progress on central government PFI projects, showed that:

Only two of the PFI building projects, due to be completed by summer 2002, were unfinished at the time of the census, and the construction of one of those has since been completed. The National Physical Laboratory at Teddington is the only project which is still yet to be completed. Where PFI buildings have been delivered late, departments have been able to defer payments or seek financial damages.

The NAO also found that most public sector project managers surveyed were satisfied with the design and construction, and performance of their PFI buildings. However, it was difficult to get a view of user satisfaction as only four of the projects surveyed had conducted formal user surveys although where surveys had been carried out they were generally positive. The NAO recommend that the government should make greater use of user surveys in future.

The NAO also says that it is not possible to judge whether the generally favourable construction performance shown by the PFI projects it surveyed could have been achieved using other procurement methods. It recommends that departments should assess the extent to which the improved construction performance in PFI projects could be achieved in traditionally procured projects.

Sir John Bourn said today:

"The theory is that PFI should incentivise the private sector to deliver good quality buildings on time and to the price agreed with the public sector. The results of our census show that this is being achieved in central government."

Notes for Editors

The NAO census covered 37 central government PFI building projects in England including 11 hospitals, seven prisons, seven roads and a number of other projects such as office accommodation and training facilities. The NAO’s coverage is of central government activity and therefore the projects surveyed excluded schools. As part of this study, the NAO spoke to construction and design industry bodies, some major PFI contractors, and independent academics.

The 1999 survey referred to above was the Benchmarking the Government Client Stage Two study, December 1999. It was referred to in the NAO 2001 report Modernising Construction (HC87 2000-01). Most of the projects surveyed in 1999 had been procured using conventional procurement arrangements.

Press notices and reports are available from the date of publication on the NAO website at www.nao.org.uk. Hard copies can be obtained from The Stationery Office on 0845 702 3474.

The Comptroller and Auditor General, Sir John Bourn, is the head of the National Audit Office employing some 750 staff. He and the NAO are totally independent of Government. He certifies the accounts of all Government departments and a wide range of other public sector bodies; and he has statutory authority to report to Parliament on the economy, efficiency and effectiveness with which departments and other bodies have used their resources.

Press Notice 09/03
All enquiries to NAO Press Office:
Tel: + 44 (0) 20 7798 7400