Executive Summary
National Audit Office Value for Money Report
- Most government projects by value under the Private Finance
Initiative (PFI) are funded by the private sector through a mix of
debt finance (in the form of bank loans or bond finance) and risk
capital (known as equity capital[Footnote 1])
provided by the shareholders of the project company.
- Previous NAO reports[Footnote
2] have shown that there are
opportunities for the investors of the equity capital to secure
benefits by refinancing on more favourable terms the debt finance
of early PFI projects which have been successfully delivered. The
improved financing terms on these projects are available as:
lending in the PFI market is considered less risky now that the PFI
market is established; the delivery risks of the projects have been
dealt with; and, in the debt markets, it is currently possible to
borrow for longer periods at fixed rates of interest which are
lower than when the early PFI contracts were let.
- Only a small proportion of a PFI projects total costs are
subject to refinancing. In most cases a refinancing will not
increase the overall financing costs of a project in cash terms
but, in improving the terms of the debt finance, will enable
payments to the investors of equity capital to be made earlier in
the contract period. The resulting benefit to the equity investors
can significantly improve the returns on their investments as their
initial investment is small (typically around 10 per cent of the
projects finance) relative to the debt being refinanced (typically
around 90 per cent of the projects finance). In the illustration of
costs measured over the whole life of a typical project
(Figure 1), 29 per cent are operating costs and a
further 54 per cent represent the cost of financing the capital
cost of the infrastructure if the Government itself funded the
project through issuing gilts. The remaining 17 per cent represents
the additional financing cost to government of the private sector
taking the risks of constructing and operating the asset for the
life of the contract (the financial risk premium).

- Before July 2002, it was not mandatory for PFI projects to have
contractual arrangements to share gains arising from debt
refinancing. Following reports by the NAO and Committee of Public
Accounts (PAC)[Footnote
3], which highlighted the particular
opportunities for the private sector to secure gains from debt
refinancing on early PFI projects, the Office of Government
Commerce (OGC), who had responsibility at the time for PFI policy,
consulted with the private sector and introduced arrangements
whereby:
- PFI contracts signed from July 2002 onwards would provide for
public authorities to receive 50 per cent of any gains arising from
debt refinancing;
- As from September 2002, a voluntary code (the Code) would apply
whereby authorities would generally expect to receive 30 per cent
of the gains from debt refinancing where their contracts had not
included arrangements to share the gains.
- The successful operation of the voluntary sharing arrangements
of the Code is important as it is the early PFI deals, entered into
before July 2002, which are likely to have the greatest potential
for debt refinancing gains but most of these deals had no
contractual mechanism for sharing these gains. In later deals, the
improved financing terms now available should be priced into the
deal when the contract is let and there are contractual
arrangements to share any subsequent refinancing gains. In December
2002, the OGC told the PAC that it expected the public sector to
receive 175 to 200 million from the introduction of the
Code.[Footnote 4] Responsibility for PFI policy was transferred from
the OGC to the Treasury on 1 April 2003.
- The opportunities to refinance the debt finance of PFI projects
have arisen as the PFI market has matured. A further development as
a consequence of the maturing PFI market and a period of liquidity
in the global capital markets has been the emergence of a market,
known as the secondary equity market, in the buying and selling of
the equity capital in established PFI projects.
- In this report we examined: n how the level of debt refinancing
gains which the Government has secured compares with the OGCs
expectations in 2002;
- how well the new arrangements to share debt refinancing gains
have been working;
- whether there are any risks for authorities from debt
refinancings; and
- how the maturing PFI market is affecting the use of equity
capital in PFI projects.
- Our examination included a cross government survey of PFI
projects. The study scope and methodology is set out in Appendix 2
and a list of the projects we surveyed is in Appendix 3.
- In summary we have found that:
- The Government has secured 137 million from PFI debt
refinancing but there has been little recent activity; (Part 1 of
this report)
- Debt refinancings may bring risks as well as benefits; (Part
2)
- There have been developments in the PFI equity market as the
PFI market has matured and financial markets have become more
liquid. (Part 3)
In terms of the overall effect on the value for money of PFI deals,
the debt refinancings that have been completed relate to only a
small proportion of PFI contracts. As we reported during
2005[Footnote 5], the increased risks to the public sector from
certain refinancings which generated large refinancing gains
through increased private sector debt made the value for money of
those refinancings questionable despite the sharing of the gains.
The Treasurys emphasis on value for money appears to be bringing
greater discipline but also a reduction in debt refinancing
activity.
- Our main findings have been:
a) Some large debt refinancings have enabled the Government to
secure gains of 137 million
The debt refinancing of PFI projects had enabled the
Government to secure the right to gains of 137 million up to
February 2006 (Figure 2). 102 million arose from
four refinancings. Three hospital deals (Norfolk and Norwich,
Bromley and Darent Valley), where the lead investors were Barclays
and Innisfree, accounted for 60 million of the Governments gains.
The investors, who retained large gains from these refinancings,
had shared 30 per cent of the gains with the public sector under
the voluntary sharing arrangements of the Code. A further 42
million of the Governments gains arose from the refinancing of the
London Underground Tube Lines project where the sharing was based
on a contractual provision and did not, therefore, rely on the
Codes voluntary sharing arrangements. The remaining debt
refinancings of early PFI deals since the Code was introduced have
mainly been undertaken on smaller projects. These have yielded
small gains for both the public and private sectors with the public
sector securing on average less than 1 million from each
refinancing. In addition, the financing of the Ministry of Defences
Skynet 5 project has been improved as part of a much wider
substantial restructuring of the project.
Figure 2 ("Table showing the right to financing gains")
is unavailable in this version of the executive
summary.
b) Refinancing gains arising from the Code have declined since
2004
The 137 million of refinancing gains the Government has secured the
right to includes 72 million from the voluntary sharing
arrangements of the Code, nearly all of which arose prior to 2005.
Only three small debt refinancings under the voluntary sharing
arrangements have been completed since December 2004 from which the
public sector will gain 0.7 million. The decline in gains from this
aspect of debt refinancing has been affected by investors taking
stock of the additional scrutiny of PFI refinancings following NAO
reports in 2005 on two of the large refinancings of the Norfolk and
Norwich and Darent Valley hospital projects. These NAO
reports, together with a subsequent PAC hearing on the Norfolk and
Norwich deal, raised concerns about large refinancing gains where
the private sector had increased its debt to accelerate the
benefits to investors. The concerns focussed on the fact that these
refinancings had been based on the public sector accepting both
increases to the liabilities it would incur to end the contracts
early and extensions to the minimum contract periods. The
authorities judged that, on the balance of current probabilities,
these arrangements would be value for money in the long term. These
conclusions could change however if the authorities wish to end the
contracts early because of changes in requirements over the next 35
years. The Treasury has re-emphasised to departments the need to
rigorously evaluate the value for money of all refinancing
proposals. This is expected to take into account any changes to
public sector termination liabilities taking account of the amounts
that the providers of both debt and equity finance would be able to
recover on termination.
The amount being received from debt refinancings, where sharing of
gains under the Code would apply, has mainly declined because the
private sector is less assured that the public sector will now
agree to further refinancings involving significant increased debt.
The private sector has less interest in taking forward other
smaller value refinancings because the time and costs involved in
arranging a refinancing of any size are considerable.
c) Gains from early PFI deals currently look likely to fall
short of the OGC estimate
Up to February 2006, the gains of 72 million which the public
sector had secured from the voluntary sharing arrangements of the
Code were well short of the OGCs 2002 estimate of 175 to 200
million. It is difficult to estimate how much more the Government
may now secure from these voluntary sharing provisions particularly
as it is currently uncertain whether the recent decline in
refinancing gains from early PFI deals will continue. In addition,
the majority of the 700 PFI contracts which have been let may not
give the prospect for the public sector to benefit from
refinancing; many are too small for refinancing to be viable,
others do not have project specific finance or there would be costs
involved in unwinding the existing financing arrangements which
could make refinancing unattractive. If there is some recovery in
refinancing activity, our current best estimate is that the total
gains to the Government from the Code are likely to increase to
between 110 and 150 million, still short of the OGCs 2002 estimate.
The OGCs estimate could, however, yet be achieved in due course if
there are any further large refinancings. The Treasury accepts that
the Government is receiving less from Code refinancings than
initially expected but its main focus has been on the achievement
of value for money through an appropriate balance of risk and
reward rather than maximising the gains. The Treasury has carried
out some initial research to identify which of the large PFI deals
may be capable of refinancing.
d) The new gain sharing appears to be generally working
well with some exceptions
Where early deals have been refinanced since 2002 the provisions of
the Code for calculating and sharing the refinancing gains have,
for the most part, been followed. Overall, the public sector has
secured the right to receive close to 30 per cent of the
refinancing gains (Figure 3) which was the
expectation when the Code was established. In line with Treasury
guidance, deals signed since 2002 are giving the public sector the
right to 50 per cent of any refinancing gains.
We found no evidence from the survey returns that the private
sector had undertaken refinancings without informing the relevant
department. We did, however, find three refinancings since the new
sharing arrangements came into force, of roads contracts let by the
Highways Agency, where the gains were not shared in accordance with
the Code. On two of these projects, the Highways Agency and Balfour
Beatty said they had been at an advanced stage of negotiating these
refinancings in 2002 before the sharing arrangements of the Code
became effective. If the gains on these two refinancings had been
shared in accordance with the Code, the public sector would have
received 1.7 million. The gains from a third refinancing, completed
by the Roadlink consortium in 2004, have not been disclosed to the
National Audit Office but the Highways Agency believes Roadlinks
gains to have been less than 1 million.
Figure 3 ("Table showing the sharing of gains") is
unavailable in this version of the executive
summary.
e) Refinancings provide scope for significantly increasing
the investors internal rate of return
In many refinancings the cash which the investors will receive over
the contract period will decrease as investors exchange later
benefits for the right to increased early benefits from the
project. The acceleration of benefits can, however, significantly
increase the internal rate of return[Footnote 6]
to investors in some cases. Most early PFI contracts were let on
the expectation of an internal rate of return to investors of 15 to
17 per cent. Where projects disclosed to us the investors internal
rate of return following refinancing these ranged from less than 10
per cent to over 70 per cent. In a fifth of these projects, all
early PFI deals, the investors internal rate of return following
refinancing had risen to over 50 per cent and, in the case of
Debden Park School and Bromley Hospital, to as high as 71 per cent.
As around half of the projects surveyed on this issue did not
disclose their investors internal rate of return there may be other
projects where there have been high internal rates of return after
refinancing.
f) The opportunity to benefit from refinancing can also
create new risks Sharing in refinancing gains has
the potential to benefit the public sector but there are also
risks. The risks relate to:
Income from refinancings involves some
uncertainty
The public sectors gains from the Code depends on continued
adherence to what are voluntary arrangements. The private sector
has said that any attempt to amend the code could jeopardise the
voluntary arrangements that have been widely complied with since
the inception of the Code. In addition, the ability to refinance
will depend on conditions in the financing market. Those
authorities which have chosen to take their refinancing gains over
time could, depending on the reasons for the termination and the
contractual terms, also face uncertainty in collecting their gains
if they were to effect an early termination of their
contracts.[Footnote 7] The future flow of income from the Code cannot,
therefore, be predicted with certainty.
There can be additional liabilities following a refinancing
Some refinancing proposals have increased public
sector risk as they have required the public sectors agreement to
possible increases in termination liabilities or an extension of
the contract period. The Treasury expects departments to carefully
assess such proposals and only to accept them if the value for
money of such proposals is fully demonstrated.
There may be service related risks
Although authorities reported they were generally satisfied with
service performance and the incentives to perform following
refinancing, it is still too early to judge whether the
acceleration of benefits to shareholders following a refinancing
will have an impact on service delivery in the longer term. The
theoretical risks are that, having taken benefits, the investors
might become less concerned about the projects performance or the
project may not have retained sufficient funds to meet future asset
maintenance obligations and unforeseen expenditure. Investors
argue, however, that, as they expect further revenues from the
projects, they will be concerned to ensure that contractors
continue to perform. The providers of debt finance are also likely
to be concerned that the repayment of their debt, which in some
cases has increased on refinancing, is not put at risk by poor
service performance. The Treasury has also observed that the terms
of financing of PFI project companies following a refinancing are
normally in line with those of new PFI deals. It therefore expects
the risks to service delivery following a refinancing to be no
different from those in new deals.
g) There are transactions which Treasury guidance excludes
from gain sharing
The Treasury accepted, after market consultation and taking account
of practicalities, that it would be unacceptable for the Government
to interfere in certain situations which would, therefore, not be
subject to gain sharing arrangements. These exclusions, set out in
Figure 10, page 18 and para 3.6, include the sale of equity shares
(although the profit on such sales will be subject to taxation).
Also, the Governments gain sharing does not extend to the way that
investors and other funders manage their portfolios of interests in
PFI projects unless this impacts on the underlying PFI contracts
which departments have entered into. These boundaries were
initially set out in Treasury guidance in July 2002 and were then
also applied to the operation of the Code. In negotiating the Code
with the private sector the Treasury acknowledged that the private
sector was making significant concessions to voluntarily share debt
refinancing gains on early PFI deals where there had been no
contractual requirement to do so.
h) There is now an emerging secondary equity market in PFI
shares
The development of a secondary market for PFI equity
has been helpful to investors who fund PFI deals and may also bring
benefits to the public sector. Whereas previously there was
uncertainty as to whether investors would be able to exit from
their PFI investments there is now a reasonably assured market for
investors to sell shares in successful PFI projects should they
wish to do so. 40 per cent of projects told us there had been a
change in the investors in their projects. In these situations
either the initial or subsequent investors may wish to also
refinance the project and we found that half of these projects had
been refinanced, a higher incidence of refinancing than in projects
where there had not been a change in investors. The sale of equity
can also help future PFI projects where the proceeds are reinvested
in other PFI deals. As the supply of PFI equity increases this
should drive down the cost of equity and improve the pricing of PFI
deals. The Treasury has said that it considers there is scope to
reduce the returns of 13 to 15 per cent which investors currently
expect when PFI projects are bid for. Further information on the
secondary market is set out in Appendix 4.
i) Funders may derive benefits from establishing portfolios
of interests in PFI projects
As the number of PFI contracts has increased there
has been a trend towards investors and debt providers building a
portfolio of interests in PFI projects.
This may enable investors to achieve operating efficiencies across
the portfolio or to improve financing terms either for the existing
portfolio or for subsequent transactions. It is possible in theory
that investors or debt providers may seek to improve the financing
of the portfolio rather than refinancing individual projects, but
there is little evidence to date of this type of activity.
j) There is limited information at present on the operation
of the PFI equity market
All authorities receive information about a PFI project companys
financial structure and the expected returns to investors when the
company bids for the contract or if it refinances the project. In
addition, Treasury guidance since 1999 has provided that
authorities should have the right to further information available
to the lenders. Nevertheless, many authorities had difficulties
providing financial information about their PFI projects to assist
this examination. Partnerships UK (PUK) records refinancings which
have been notified to it and also launched in 2005 a database of
PFI projects which includes financing information. However,
considerable further work is needed to make aspects of this data
accurate and comprehensive and this will require the support of the
authorities. The profits or losses which investors may derive from
selling shares in PFI project companies are not disclosed to
authorities because the contract is between two private sector
parties.
Recommendations
Recommendations arising from previous NAO and PAC
refinancing reports are set out in Appendix 5 together with a
commentary from the Treasury on progress in implementing these
recommendations. Recommendations arising from this current
examination are set out below.
Criteria for accepting refinancing proposals
- The Treasury should continue to support authorities in ensuring
that value for money is achieved in refinancing. It should continue
the steps it has taken to articulate to the PFI market the public
sectors criteria for accepting refinancing proposals, particularly
those involving changes to termination liabilities. The Treasury
should also continue its efforts to identify and disseminate
examples of good practice in the treatment of termination
liabilities and other refinancing issues.
- Before accepting a refinancing proposal, an authority must give
careful consideration to the impact of the proposals on the future
of the project, in particular:
- whether, after investors have withdrawn benefits from the
project, there will still be sufficient incentives to perform the
required services and sufficient reserves within the project to
fund the life cycle maintenance of the project and contingencies;
- the consequences of accepting any proposal to increase
termination liabilities, or extend the contract period,
particularly given that unforeseen events may arise in the future,
such as changes in public service requirements or contractor
performance, which could increase the likelihood of early
termination of the contract needing to be considered; and
- that, depending on contract terms, receiving the gain over time
may create a possible risk that part of the gain might not be
received if the contract is terminated early. Decisions on the best
basis for receiving the gain should take into account this risk and
other aspects of value for money such as the impact on termination
liabilities.
Transactions excluded from gain sharing
- As Treasury guidance permits a number of financing transactions
which would not lead to gain sharing, the Treasury should monitor
these transactions to ensure that the primary motivation of the
private sector entering into such transactions is not to avoid
sharing refinancing gains.
Monitoring of the extent to which projects may be capable of
refinancing
- As there are now 700 PFI contracts in existence, the
Treasury should extend the work it has been doing on considering
the capability of large projects to refinance, to form a view on
the proportion of the 700 contracts which might be suitable for
refinancing. Consideration of whether contracts are suitable for
refinancing should take into account whether they have fixed
interest arrangements which are coming to an end which might
present refinancing opportunities.
Monitoring the cost of PFI finance
- Current expectations are that the increase in sources of equity
arising from the emerging PFI secondary market should drive down
returns which equity providers seek from PFI projects. Debt finance
should continue to be provided at competitive rates reflecting the
lower risks now the PFI market is established. In order to
demonstrate whether these expectations are achieved, the Treasury
should make use of the new PUK project database to produce an
annual summary of the trends in PFI financing costs.
Improved transparency in the returns to investors from PFI
projects
- To provide transparency and a better understanding of the
dynamics of PFI equity investment, further information is required
on the full range of costs and benefits which investors experience
from participating in the PFI market. Part of this information
should be provided by authorities making more extensive use of
their contractual rights to information. To provide the full
picture of the investors experience from their involvement in the
PFI market, the Treasury should discuss with investors what further
information they could provide which would illuminate this
issue.
- [back from footnote 1]Equity capital is usually a mix of
ordinary shares and subordinated debt (debt that ranks behind the
main debt on repayment).
- [back from footnote 2]Previous NAO and PAC reports dealing
with PFI refinancing are set out in Appendix 1.
- [back from footnote 3]Appendix 1.
- [back from footnote 4]Report from the Committee of Public
Accounts: PFI refinancing update (HC 203, June 2003).
- [back from footnote 5]NAO reports on Darent Valley Hospital:
the PFI Contract in Action (HC 209 2004-05) and The Refinancing of
the Norfolk and Norwich PFI Hospital: how the deal can be viewed in
the light of the refinancing (HC 78 2005-06).
- [back from footnote 6]See paragraphs 1.36 and 1.40 for further
explanation of this measure of investor returns. The improved debt
financing terms which contributed to increases in investors'
internal rates of return should be available to the public sector
in current procurements reducing the likelihood of later
refinancing gains.
- [back from footnote 7]See paragraphs 2.4 to 2.5 and Appendix 9
for further explanation of the risks associated with taking the
gain as a lump sum or over time.