Executive Summary
National Audit Office Value for Money Report
Since it was set up in 1994, the Heritage Lottery Fund (the
Fund) has awarded 3.8 billion of lottery funding to some 24,000
(Footnote a) heritage projects. This
report looks at how the money has been spent, what has been
achieved and the responsiveness and effectiveness of the Funds
grant- making processes. We carried out a detailed review of 30
funded projects by interviewing applicants, visiting the project
and examining the Funds case files. We also surveyed 8,000
applicants of whom 2,372 responded, interviewed staff in three of
the Funds 12 regions and conducted a focus group of external
consultants used by the Fund. Our methods are described in more
detail in Appendix 1.
Our main findings are:
- The Fund has three primary aims: to conserve the UKs diverse
heritage, to encourage people to be involved in their heritage and
to widen access and learning. Although the overall impact of the
Fund is difficult to measure, there are good indications that the
projects it has funded are delivering against these aims and that
the benefits achieved are being sustained.
- The Fund aims to achieve a spread of grants across the United
Kingdom by allocating around 60 per cent of the available funding
to regions on a per capita basis and targeting local authority
areas which have received little of the Funds grant. There are,
however, wide differences between regions in the total amount of
grant awarded, reflecting the volume and type of applications
received. London has received the most funding on both an absolute
and per capita basis. Northern Ireland has received the least
funding on an absolute basis, whilst the South East of England has
received the least on a per capita basis. The Fund has been
successful in boosting applications in targeted local authority
areas.
- The availability of lottery funding has been a critical factor
in the achievement of project benefits; 55 per cent of
applicants surveyed said their project would not have gone ahead
without the Funds grant whilst a further 42 per cent would have
tried to find alternative funding or reduced their project scope.
If offered less grant, 25 per cent of applicants surveyed said
their projects would not have gone ahead whilst a further 70 per
cent would have tried to find alternative funding or reduced their
project scope.
- Most projects have been delivered to cost; some 17 per cent of
completed projects have gone over budget and 6 per cent of all
projects have received additional grant, averaging 176,000, to help
meet cost increases.
- Most projects have been delivered on time; 26 per
cent have been delivered late, half of these taking an additional
six months or longer. The average time from application to
completion is two and a half years for projects awarded less than
50,000 and over four years for larger projects.
- Overruns were mainly due to unanticipated events during
construction and poor planning. Inflation was a significant cause
of cost overruns. Some applicants lack project management skills
and many applicants would welcome more support from the Fund and
more opportunities to learn from one another.
- The Funds grant-making processes are robust and practical and
its staff knowledgeable and helpful. Since the 1990s, it has
greatly improved the swiftness with which it assesses applications
and gets projects started, however, the majority of applicants
continue to find the process of getting grant burdensome. The Fund
is developing plans to simplify its grant-making processes which it
intends to implement during 2008.
Conclusion on value for money
Our overall conclusion is that the Fund has been successful in
supporting projects which are helping to preserve the heritage of
the United Kingdom and make it more accessible. Its robust
processes and thorough approach to assessing applications have led
to better, more sustainable projects. It should do more, however,
to reduce the burden on applicants, promote swifter delivery of
projects and provide better support to those who need it.
Recommendations
The recommendations below focus on the key areas for improvement
identified in this report, taking into account work already under
way within the Fund to improve its procedures and to manage the
effects of the expected reduction in income as a consequence of
National Lottery funding of the Olympic and Paralympic Games.
- In redesigning and
simplifying its application procedures the Fund
should:
- keep its approach to risk under review so as to ensure
that it does not impose unnecessary burdens on applicants.
In particular, in moving to a new two stage process, it must adopt
with confidence the principle of taking decisions at the early
hurdle stage based on limited information.
- make it a priority to clearly identify and communicate
to applicants the information the Fund needs to make a
decision. The Fund recognises that it could be more
specific in its application forms and guidance about the
information it needs and that some applicants find the Funds
requirements confusing. Reducing the need to seek clarification and
supplementary information from applicants would reduce the burden
on them and help speed the process up.
- The Fund should
ensure that the assessment of applications starts
promptly. The Fund has succeeded in reducing average
assessment times, but there is scope to assess some applications
more quickly. Delays in assessment are associated with failing to
get the process under way when an application is received.
- Whilst responsibility for
project delivery rests primarily with applicants, the Fund has a
vested interest in seeing that project benefits are delivered
within budget and as quickly as possible. To reduce time
and cost overruns, the Fund should:
- monitor delays in project delivery at an aggregate level so
that it can identify the extent of delays within each grant
programme and region and have a basis for assessing its progress in
reducing time overruns;
- develop and extend the support and training it offers
applicants in aspects of grant and project management, for example
the Fund could alert projects to delivery risks and encourage them
to assess their own competence and address weaknesses;
- set in place a system to promote the sharing of the knowledge
and experience between applicants so that all applicants have the
opportunity to learn from the experience of other projects;
and
- review, within two years, the way in which recent changes to
its project monitoring system are impacting on applicants and
project delivery.
- The Fund should
review its approach to partnership funding to ensure that it is
getting the most from the lottery funding available. The
ease with which applicants can raise partnership funding varies
from project to project depending upon a number of factors
including the applicants own resources, their fundraising
expertise, the external funding climate and the appeal of the
project to potential funders. As part of its plans to manage the
anticipated downturn in funding leading up to the Olympic and
Paralympic Games, the Fund should consider whether the funding
ceiling for individual projects is set at the right level.
- The Fund should
continue to develop its framework for capturing the benefits
arising out of its funding so that it can measure and report on the
impact it is having, and seek to complete this work by March
2008.
- [back from footnote a] Including 15,000
grants, totalling 125 million, made through programmes funded by
the Heritage Lottery Fund but administered by other bodies (see
Endnote 4).