Figure 1: The Defence Information Infrastructure
Vision:
A single information infrastructure
- for the three Services and the central
Ministry of Defence;
- to facilitate joint working between users
on a common platform;
- to enable 12 key defence change
programmes including:
- change programmes requiring personnel to use new software
applications, such as the Joint Personnel Administration
application,
a human resources and pay system for the three Services; and
- change programmes involving the re-location of large numbers of
personnel, such as Project Hyperion to merge the two bodies
which run the Army to form a single headquarters.
The defence change programmes are essential for the Department
to deliver its Gershon efficiency targets.
Requirement:
DII Scaling The programme will deliver
- approximately 150,000 terminals;
- for approximately 300,000 users who will be
office-based, mobile or deployed on operations; and
- to over 2,000 sites worldwide including
operational theatres and Royal Navy vessels.
Security The programme will deliver a
system capable of operating at all
security levels, which will be fully accredited.
Applications The DII system will allow access
to approximately 1,000 applications.
Other Benefits The system will allow
joint working on a common platform across the
whole Department, which will facilitate
more collaboration and easier communication.
Delivery Partner:
DII is contracted to the ATLAS
Corporation, a consortium comprising:
- EDS (the prime contractor)
- Fujitsu
- EADS
- General Dynamics
- Logica CMG
ATLAS was formed specifically to bid for and deliver the DII
contract
In the consortium Fujitsu shadows the capability of EDS. EADS,
General Dynamics and Logica CMG shadow each other.
Commercial Structure:
The Department let a 10 year contract from 21 March 2005 for
DII.
The key contracted deliverables are:
- applications that are compatible to be
accessed via DII;
- a system that can be deployed in operational
theatres;
- a single managed service for users with
a single point of contact for all queries, which
will be measured through Key Performance Indicators; and
- the management of the Department’s principal
legacy systems until they are replaced by
DII.
The contract includes mechanisms to manage change in
implementation requirements, in recognition that the Department and
the three Services are undergoing considerable structural and
operational change which will impact on the Programme.
The contract was structured to minimise the risk to the
Department of poor contractor performance:
Contractor shadowing
The consortium is structured so that there can be no single point
of failure – each contractor in the consortium is shadowed by a
competitor with equivalent capability that would be able to step-in
to deliver the programme requirements in the event of a
catastrophic performance failure or contractor withdrawal.
Incremental approach
The programme is divided into increments which are separately
contracted for. This allows the Department to drive contractor
performance at key times and could be used to put future increments
out to external competition in the event of a catastrophic
performance failure by the consortium.
The programme was originally split into three increments but has
been sub-divided further into a total of seven increments.
Payment on Performance
Payment for DII is made through charges for DII terminals and user
accounts so that the contractor recoups the majority of its
investment through performance-based payments. Charges are set at
different rates for different user types. Different charges apply
for Software Release 1, a flat rate, and Software Release 2, which
has banded charges based on the volume of users and terminals.
Programme Costs:
The forecast programme cost at contract let was £5,854
million. The full cost of the programme could not be
estimated until further assessment work was completed to define the
scope of the requirements for the Deployed and Top Secret
capabilities.
The current forecast cost for the DII programme
and programmes on which it is dependent, such as the provision of
wide area support services, is £7,093 million, including an amount
set-aside to manage future risks. This is the forecast cash cost,
including the costs of Departmental resources to manage the
programme. It does not include additional accounting costs to the
Department such as for depreciation.
State of Infrastructure being replaced:
Systems DII is replacing approximately 300
legacy systems across the three Services and the main Department,
ranging from highly specialised systems with few users to systems
providing standard office administrative tools, such as CHOTS and
NavyStar. Many of the legacy systems are not compatible with each
other and some do not have inbuilt security features. A number of
the systems were very old, did not provide the required range of
functionality to users, had become difficult and costly to maintain
and upgrade and did not deliver the capability required by the
current defence change programmes.
Applications Before DII, the Department had
many different versions of common applications, because IT was not
delivered centrally. The DII Programme rationalised the number of
applications used in the Department, reducing the number of
applications from over 6,000 to around 1,000 before letting the
contract.
Physical Estate The defence estate in which DII
is being installed is highly variable, ranging from the newly
refurbished Headquarters in London to small, poorly maintained
Territorial Army facilities.
DII(Convergent) The Department had to develop a
shortterm system solution while it was devising the requirement for
the DII Programme to replace some existing systems. The system,
DII(Convergent), was designed and maintained by Fujitsu. It has
been installed in a number of locations, including the Department’s
Main Building in London which was completely refurbished between
2000 and 2004.
From 2003 to date, the Department has approved expenditure of
£426 million to develop and support 25,000 DII (Convergent)
terminals.
When it was installed, DII(Convergent) was the most functionally
rich system that the Department had, allowing collaborative working
and electronic document and record management. Many of the
requirements of DII(Convergent) are similar to DII, although the
system architecture has not been copied.
Source: National Audit Office analysis
| Increments on
contract |
| Original Increment Structure |
Increment 1 |
Increment 2 |
| Current Increment Structure |
Increment 1 |
Increment 2a |
Increment 2b |
| Increment Scope |
Fixed DII infrastructure, including on Royal Navy vessels, to
replace legacy systems with DII at Restricted and Secret
levels. |
Fixed DII infrastructure to replace legacy systems with DII at
Restricted and Secret levels. |
Deployable systems and services |
| |
The provision of a managed service for DII and legacy
systems. |
The provision of a managed service for DII and legacy
systems. |
|
| Contract award date |
21 March 2005 |
29 December 2006 |
27 September 2007 |
| Number of terminals including DII(C)
(18,500) |
72,000 (69,200 after the Medium Term Work Strands) (62,800
excluding maritime rollout) |
44,000 |
3,332 terminals. 1,608 to be deployed |
| Number of users |
201,500 (195,100 after the Medium Term Work Strands) |
57,500 |
Undefined |
| Number of sites |
680 locations, including Royal Navy vessels |
660 locations |
78 different Headquarters plus Royal Navy vessels |
Note
For a guide to all increments, including those not yet on contract,
see Appendix 3.