Executive Summary
National Audit Office Value for Money Report
- A growing proportion of the UK's civil public sector nuclear
facilities have reached, or are nearing, the end of their
operational life. By December 2007, 14 facilities had already shut
down and were in the process of being decommissioned, which
includes cleaning-up the sites. [Footnote 1] Parts of Sellafield
the UK's largest civil nuclear site were also being decommissioned
and cleaned-up. Current plans envisage that most of these sites
will be cleared over a 100-year period. The current best estimate
puts the undiscounted future costs of decommissioning sites at
around 61 billion at 2007 prices.
- The Nuclear Decommissioning Authority (the Authority) was
established on 1 April 2005 to ensure the safe and efficient
clean-up of the UK's first generation of civil public sector
nuclear facilities. It owns a varied and ageing portfolio of 19
sites. [Footnote 2] The sites include: Magnox nuclear power
stations; research sites, including Dounreay; and the fuel
handling, recycling and production facilities at Sellafield. The
Authority is a non-departmental public body sponsored by the
Department for Business, Enterprise and Regulatory Reform (the
Department), which approves its strategy, plans and budget. The
Authority also reports to the Scottish Ministers who agree its
strategy and plans for Scottish sites, and thus the Department and
the Scottish Government are involved in the Authority's
governance.
- The Authority discharges its responsibilities for
decommissioning through management and operation contracts with
licensed operators at each site. These site licensees manage sites,
including preparing site plans, performing and sub-contracting
work. The site licensees are, in turn, owned by parent bodies. The
relationship between the Authority and the parent body is governed
by a parent body agreement. At December 2007 the parent bodies
comprised: the United Kingdom Atomic Energy Authority, a
non-departmental public body; British Nuclear Group Limited (part
of British Nuclear Fuels Limited, a company wholly owned by
government); Reactor Sites Management Company Ltd, part of the
private company EnergySolutions; and Westinghouse Electric Company,
part of the Toshiba Group.
- The UK Government set out, in broad terms, the structure for
taking forward decommissioning in the 2002 White Paper Managing the
Nuclear Legacy Cm 5552. The structure is intended to allow the
Authority to put the right to be the parent body out to competition
whilst retaining the skills and or knowledge of staff within the
site licensees. This avoids the need to license a new operator
after each competition. The Government believes competition will
stimulate innovation and bring strengthened management to the
decommissioning process. The first of these competitions, to become
the parent body for the Low Level Waste Repository near Drigg, is
expected to be concluded by the end of February 2008 subject to
Government approval. The competition to become the parent body for
the Sellafield group of sites [Footnote 3] is underway and due
to be concluded by the end of 2008. The contracts are expected to
run for an initial period of five years, extendable for a total of
12 further years over three periods, subject to performance.
- The Energy Act 2004 imposed a duty on the Authority to
safeguard the environment; maintain health and safety; and preserve
nuclear security. The Act left the statutory responsibilities of
site operators, and their relationship with health, safety,
security and environmental protection regulators, unchanged.
Ultimate legal responsibility for determining how to comply with
regulatory requirements remains with the site licensees. As such
there are limits on the extent to which the Authority or the parent
body can influence how the site licensee delivers the work paid for
by the Authority. Figure 1 summarises the
relationship between the different parties.
- The Authority's income comes from a mix of grant-in-aid from
the Department (expected to be 1,420 million in 2007-08) and
revenue generated from commercial activities (budgeted to be 1,370
million in 2007-08), including power generation and fuel
processing, that are centred on four of its sites. In 2006-07, the
Authority spent around 690 million on project work at
decommissioning sites, of which 40 per cent was spent at Sellafield
(see paragraphs 1.13 and 3.2).
- This report examines the Authority's performance in using its
contracts to take forward the decommissioning of sites since April
2005, and the lessons it can learn for contracting as it takes
forward its competitions. The Authority's management of the
competition process will be considered in future reports.
Overall conclusions and assessment of value for money
- The nature and scale of the decommissioning task inherited by
the Authority was highly uncertain. Many of the Authority's sites
had not been designed with decommissioning in mind, and
record-keeping particularly in the early days of nuclear
development had not always been sufficiently detailed to inform
decommissioning several decades later. Since its creation, the
Authority has invested significant effort in determining the scale
of the task it faces in decommissioning the UK's first generation
of civil nuclear facilities. The Authority has produced, for the
first time in the UK, a unified strategy for decommissioning the
UK's legacy nuclear sites.
- The Department and Authority envisaged that better definition
of the decommissioning task would see estimates of remaining
lifetime costs grow in the short-term, but stabilise by 2008 and
fall thereafter. The most recent iterations of the Authority's
plans have continued to produce large increases in estimates,
including the cost of the work programme over the next five years
which might have been expected to have stabilised by now. The
continuing instability in these costings reduces their value during
the parent body competitions, making it difficult for the Authority
to judge the cost and price element of bidders proposals.
- Significant resources have been allocated to the
decommissioning programme. But the progress made by the Authority
in decommissioning non-operational Magnox and research sites has
been hampered by emerging pressures on its financial position. Due
to the need to fulfil additional urgent expenditure commitments,
particularly at Sellafield, and the uncertainty of commercial
income from its ageing and unreliable facilities, the Authority has
had to make changes at short notice to some sites funding levels
for the last quarter of 2006-07 and for 2007-08 to meet its
priorities within budget. These changes have created significant
uncertainty for both site licensees, in planning and delivering
their long-term decommissioning programmes, and their contractors,
and have led to additional costs for the taxpayer which lessen the
value for money derived from the decommissioning programme.
- The Authority's use of cost reimbursement management and
operation contracts with site operators has been a sensible
approach to adopt whilst establishing its role as a purchaser of
decommissioning services. But these contracts require reliance on
detailed short-term annual work programmes, which change frequently
and make it difficult for the Authority to maintain a sufficiently
testing incentive regime. In our view, in their current form, the
contracts are unlikely to encourage sites to deliver long-term
value for money as they do not provide strong incentives to
contractors to control lifetime costs through, for example,
innovation and efficiency improvements. Other forms of contract,
better adapted to the circumstances of particular sites and work
streams, and the long-term nature of the work, need to be adopted
if the potential value for money benefits of competitive
contracting for decommissioning work are to be fully realised. The
Authority has indicated its intention to move towards more testing
contract forms where this is appropriate. It will need to have a
clear view of how to achieve this if it is to use the competition
process effectively to deliver benefit for the taxpayer.
Figure 1 ("The key responsibilities of the main
organisations which oversee, manage and regulate the
decommissioning of civil public sector nuclear sites") is
unavailable in this version of the executive summary.
Note: The diagram does not show the relationship at December 2007
between the Department and two of the parent bodies. The Department
sponsors the united kingdom Atomic Energy Authority, which is the
parent body and site licensee for Dounreay and the other research
sites. The Department owns British Nuclear Fuels Limited which
includes the parent body for the Sellafield site licensee. British
Nuclear Fuels Limited is not competing to remain the parent body of
Sellafield.
Our main findings
- The Authority has
developed a comprehensive and consistent framework for drawing up
decommissioning plans, known as lifetime plans, at site level. The
quality of the plans has improved over a number of iterations
particularly in setting out what needs to be done and, in broad
terms, how it might be done and when (see paragraphs 2.2 and
2.3).
- The Authority's 2007
estimate of the undiscounted future costs of sites over their
remaining lifetime (73 billion [Footnote 4]) was almost 17
billion (30 per cent) higher than the estimate made by the
Department in 2003. [Footnote 5] Between 2005 and 2007
lifetime costs increased by some 18 per cent (11.7 billion), after
adjusting for inflation and the Authority's expenditure at its
sites since it was established in 2005. In part, this increase
reflects a more complete assessment of the range of work that needs
to be taken forward, including the action necessary to address
hazard at some of the legacy facilities at Sellafield. Our analysis
of the plans also indicates, however, that cost estimates on work
expected to be undertaken in the near to medium-term, which might
be expected to have stabilised by now, have risen significantly
over successive iterations. Between 2005 and 2007, the estimate of
likely costs for the first five year period covered by those plans
in a consistent manner [Footnote 6] April 2008 to March 2013
rose by 41 per cent (see paragraphs 2.4 to 2.8 and Figure 8 on page
18).
- In deriving cost estimates
from the site licensees, the Authority has obtained most of its
assurance about the validity of budgets by specifying the costing
procedures sites should adopt and reviewing compliance with those
procedures. The Authority's staff, including its engineers, review
project budgets included by sites in lifetime plans. The degree of
scrutiny has been limited, however, as the Authority does not, for
example, routinely employ its own professional cost advisers to
review estimates. The Authority has previously recognised the need
to strengthen the scrutiny of costs and is intending to commission
a validation of the costs being submitted by sites in the lifetime
plans to be finalised in 2008 (see paragraphs 2.9 to 2.11 and
Figure 9 on page 20).
- The Authority reports
annually on performance at each of its sites by providing data on
the value and cost of work completed against budget and assessing
progress against key milestones and deliverables, for example
expressed in terms of the demolition of buildings on site. These
measures do not convey clearly to the lay reader how far
decommissioning has progressed down the path from waste
characterisation, through retrieval and containment, to hazard
removal and eventual site clearance. The Authority has set itself a
target for 2007-08 to develop, for all potentially mobile
radioactive wastes, a hazard baseline that will cover the amount of
waste, its activity, location, condition and the percentage of
waste that is passively safe. [Footnote 7] If robust hazard
baselines can be developed, it is possible that these might provide
one basis for reporting progress on decommissioning. At present, in
the absence of appropriate measures of progress, the focus of
external parties monitoring the Authority's performance is likely
to be skewed towards levels of spend rather than its outputs and
outcomes (see paragraphs 3.3 to 3.5 and Figure 10 on page 22).
- It is still too early to
judge the impact of the contracting regime on health, safety,
security and environmental performance. Since 2000-01, there has
been a general reduction in the number of reported nuclear safety
events at the sites now falling within the Authority's
responsibility. Site by site performance against a wider series of
metrics developed by the Authority was reported, for the first
time, in its 2006-07 Health, Safety, Security and Environmental
Report. The Authority can expand the range of metrics its uses and
reports on so it can, for example, assess the overall environmental
impact of its sites (see paragraphs 3.7 to 3.8 and Figure 11 on
page 23).
- The Authority has not had
sufficient flexibility in its budget to cope with the level of
volatility and uncertainty it has faced with its commercial income,
and urgent expenditure commitments, in particular at Sellafield. As
a result, a pattern of start and stop on some non-operational
Magnox and research sites has incurred extra costs for the
taxpayer. In November 2007 the Authority consulted on its plan to
increasingly focus its decommissioning resources over the next
three years on the high hazard facilities at Sellafield and
Dounreay. The speed with which the Authority can move resources
between sites depends on factors such as: the potential
socio-economic impact on those areas around smaller research and
Magnox sites; having funds to cover transition costs such as
redundancy; and the ability of Sellafield and Dounreay to make
effective use of new money (see paragraphs 3.11 to 3.17 and Figure
12 on page 25).
- The Authority has lacked
an established mechanism, developed and applied in consultation
with stakeholders, for deciding priorities against different
resource assumptions. As at Autumn 2007, the Authority was in the
early stages of developing a framework to demonstrate the overall
value of decommissioning work, for example, on levels of hazard,
environmental performance and its socio-economic impact on local
communities. It plans to use this framework in comparing different
decommissioning scenarios (see paragraphs 3.5 and 3.23 to
3.24).
- The Authority has had to
strike a balance between encouraging sites to take forward
decommissioning in a cost effective way and not cutting across site
licensees legal responsibility for all site activities. The
appointment of new parent bodies, drawn from the private sector, is
creating a new set of relationships to manage. The Authority, the
Health and Safety Executives Nuclear Directorate, the site
licensees and existing parent bodies, have sought to clarify the
roles of the different parties but this framework remains
relatively new and untested. The effectiveness of this framework in
helping the Authority take forward the decommissioning task will
rely heavily on the ability of all parties to work in partnership
towards common shared goals, with incentives in place that reflect
those goals, and management teams with the skills to work
constructively with their partners (paragraphs 4.3 to 4.5).
- The use of a common cost
reimbursable management and operation contract across all sites has
provided a stable framework upon which the Authority and its sites
have been able to establish consistent industry-wide planning and
contract control procedures. The use of these contracts has,
however, meant that increases in site licensees costs are borne by
the taxpayer. And because of the difficulties of using short-term
incentive regimes noted at paragraph 11, the contracts are not well
suited to the delivery of decommissioning activities that generally
run to longer timescales. There is scope for the Authority to make
greater use of fixed cost, or longer-term target cost plus fee
arrangements to cover support services and those decommissioning
activities, such as demolition or deplanting of non-radioactive
buildings, that do not entail substantial risk or uncertainty and,
in doing so, deliver better value for money. The Authority is
considering, through the competition process, how it can use more
commercial payment and reward mechanisms, including the use of
multi-year performance incentives (see paragraphs 4.6 to
4.29).
Recommendations
- The Authority should develop its current contract
incentives by:
- incorporating elements of fixed price, or longer-term
target cost plus fee, for work streams or sites where
analysis of risks – including awareness of experience
abroad – indicates that work scope and cost are
sufficiently well defined;
- reviewing intellectual property provisions to
maximise the Authority’s share of the benefits of
innovation while providing sufficient incentive for
site licensees and their parent bodies; and
- moving to multi-year performance milestones
aligned with project timetables where financial
flexibility permits.
- The Authority should strengthen its capacity to
scrutinise the cost estimates put forward in the lifetime
plans submitted by sites. The Authority has recognised the
need to strengthen its scrutiny of costs and is intending to
commission a validation of sites’ 2008 plans.
- The Authority should determine the reasons for the
continuing increases in cost estimates submitted by sites,
particularly on those elements of work which by now
should have been reliably costed. The analysis could break
down cost increases into those driven by: changes in the
Authority’s policy or guidance; better understanding of
work required to achieve regulatory compliance; changes
in the volume or characterisation of waste; and changes
in the strategy, costs or scope of the work proposed by
the site licensee. The Authority should seek to quantify
uncertainties associated with the lifetime cost estimates
that it intends to publish, and then present a cost range
within which the final figure is likely to fall.
- In the absence of stable cost baselines the Authority
must consider how:
- it will compare the likely cost outcomes of bidders’
proposals against each other and against the
probable cost under the current incumbents;
- it can subsequently lock successful parent bodies,
and their site licensees, into price and incentive
regimes which will provide the taxpayer with good
value, once work scope has been adequately defined
but where the successful bidder may already have
been appointed.
- The Authority should evaluate the risks from
more commercial management of its sites following
competitions and ensure that its contract management
staff are equipped to mitigate those risks.
- The Authority should develop clear and transparent
measures of the progress being made against the objective
of decommissioning sites and present these in public
documents in a way which is comprehensible to the
layman. Its current work on developing a hazard baseline
could provide a possible means of developing such
measures. It should also continue to develop, by working
with the regulators, the metrics its uses to monitor and
report on the health, safety, security and environmental
performance of its sites.
- The Authority should require site licensees to prepare
lifetime plans on the basis of the most realistic available
funding assumptions and reject plans that exceed those
limits unless the sites are able to demonstrate to the
Authority they are the minimum necessary to meet
their obligations.
- The Authority should require lifetime plans to be
prepared in a form which enables sites to assess the
impact of differing funding assumptions for the near term.
Sites would then be well-placed to provide the Authority
with the information it needs to assess priorities should
funding levels change.
- The Authority should work with parent bodies,
site licensees and regulators to develop a shared
and documented understanding of their roles and
responsibilities given the complexity of the contracting
regime and the need to agree, prioritise and meet
regulatory requirements as they arise.
- At the end of 2007 the Department transferred
responsibility for governance of the Authority to its
Shareholder Executive, which is responsible for improving
the way Government manages public sector businesses.
The Department should ensure these new arrangements
enable it to be fully aware of developing financial
and other major issues affecting the decommissioning
programme and enable it to assess key risks to the
Authority’s programme.
- The Department, working with HM Treasury and
the Authority, should ensure that decisions on the use
of funding flexibilities available to the Authority are
made promptly in response to unanticipated changes
in commercial income or commitments, to minimise
their adverse impact on the value for money of the
decommissioning programme and the confidence of the
supply chain.
- The Department should ensure that the targets
which will underpin the 2008-11 Departmental Service
Objective – to manage energy liabilities effectively and
efficiently – provide incentives for the Authority to bear
down upon and control lifetime costs.
- [back from footnote 1] In this report we use the
term decommissioning in a broad sense to cover the range of
activities required to take a facility which has ceased operating
to its end state.
- [back from footnote 2] The Authority has full
ownership of 18 sites and has a lease agreement with the United
Kingdom Atomic Energy Authority for that part of the Harwell site
which was designated to it under the Energy Act 2004 and requires
decommissioning and clean-up.
- [back from
footnote 3] The parent body will own the shares in the site
licensee for Sellafield, Capenhurst, Calder Hall and
Windscale.
- [back from footnote 4] This figure, at 2007 prices,
comprises 61 billion for decommissioning (mentioned at paragraph 1)
and around 12 billion to cover the cost of running the remaining
operational facilities to the end of their commercial life, but
does not reflect the anticipated revenue from these sites.
- [back from footnote 5] Estimated cost had increased
partly as a result of inflationary pressures (which have added
approximately 2 billion per annum, the equivalent of 8 billion over
the period 2003 to 2007), and even though resources have been spent
on operating and decommissioning sites during the intervening
period.
- [back from footnote 6] Although all three plans
covered 2007-08, the basis for treating the costs of contingency
for that year varied.
- [back from footnote 7] Waste which is passively safe
includes: waste which is in a form which is chemically and
physically stable and is stored in a manner that minimises the need
for safety mechanisms, maintenance, monitoring and human
intervention.