Executive Summary
National Audit Office Value for Money Report
Background
- The strategic road network in England consists of 4,800 miles
(7,700 km) of trunk roads and motorways. The Highways Agency (the
Agency), an executive agency of the Department for Transport, is
responsible for the network. In the past, the Agency's focus was on
building and maintaining roads rather than managing their
operation. In 1998, the Government announced that the role of the
Agency was to change to that of a network operator with objectives
to reduce traffic congestion through improved traffic monitoring
and travel information.
- The Agency considered that it needed improved motorway
telecommunications systems to carry live data about traffic
conditions. Most of the Agency's existing systems were the result
of nearly 40 years of piecemeal development. Along the motorway
network, the telecommunications systems used copper cable to carry
voice and data signals, but transmission capacity was limited. By
1998, the Agency had installed fibre optic cable along half of the
motorway network, principally to carry CCTV camera images. Parts of
the network had been upgraded to digital technology, but most areas
used obsolete analogue equipment which was no longer supported by
the telecommunications industry. If left unaddressed, the continued
use of analogue technology would have left the Agency with
insufficient capacity to fulfil its role as a network
operator.
- The Agency decided to upgrade all its telecommunications
systems to digital technology. The work would include laying 278 km
of high transmission capacity, fibre optic cables to the existing
2,222 km fibre optic cable network (Figure 1). After receiving first round bids, the
Agency, on affordability grounds, reduced the amount of cable
laying to 110 km. Some omitted lengths were not dropped from the
project but transferred to a programme of future investment that
the Agency can call off from a pre-priced schedule of additional
works, when the work is needed and funding is available. By the
time of the award of the contract, other lengths had been completed
by the Agency (Figure
2).
Figure 1 ("In 2003, the original tender documents included
extending the Agency's fibre optic cable network by 278
kilometres") and;
Figure 2 (" On affordability grounds, the Agency reduced the
extension to its fibre optic cable network under the NRTS contract
from 278 kilometres to 110 kilometres")
are unavailable in this version of the executive summary.
- In September 2005, the Agency and GeneSYS Telecommunications Ltd, a special
purpose company owned by Fluor Corporation and HSBC, signed a 10½-year Public
Private Partnership (PPP) contract to upgrade, operate and maintain the
telecommunications cables and transmission equipment located alongside the
English motorway network. The Agency structured the contract so that:
- Upgrading and operating the telecommunications systems were captured in a PFI
type structure. As is common with this type of arrangement, GeneSYS agreed to
finance the upgrade works and in return will receive a contractually set,
monthly charge of £3.7 million (2004 prices) from the completion of the upgrade
through to the end of the contract, provided the services meet the Agency’s
performance requirements.
- The Agency can order changes to the telecommunications systems (including
extensions to the coverage of the fibre optic cabling) from the pre-priced
schedule of additional works. Under the related provisions, GeneSYS’s prices
cover the direct costs of all the work required to implement the ordered
changes.
The eventual lifetime cost of the contract therefore depends on the number and
value of additional services ordered from GeneSYS. At contract award, the Agency
assumed that the 2004 present value of its payments under the contract would be
£385 million, the mid-point of a range from £255 million to £515 million (2004
prices), depending on the value of the called-off additional works.
- From October 2007, following a two-year upgrade of the cable network, roadside
devices such as message signs and CCTV cameras may now be linked to traffic
control centres through up to date digital telecommunications systems. This
project is known as the National Roads Telecommunications Services (the NRTS).
Findings
- We examined the procurement of the project. Our main findings are as follows.
- The Agency had good value for money grounds for transferring the risks of
major cost and time overruns inherent in such a large telecommunications
project. The Agency procured the project as a PPP because it transferred risk to
a contractor that had borrowed money to upgrade the systems and had something to
lose if things went wrong.
- At the pre-qualification stage, two of the higher scoring potential bidders
withdrew from the tendering process. Six potential bidders for the project were
identified early on but interest wavered during the extended time taken to
produce the bid documents. Concerned that some of the potential bidders might be
losing interest, the Agency took the unusual step of issuing a second
advertisement. Two of the higher scoring potential bidders did not re-apply.
Later on in the tendering period, the competitive field reduced further when two
bidders that had responded to the second advertisement dropped out of the
running, one because of doubts over the financial viability of a consortium
member and the other because of doubts that its proposed technical solution
could be developed sufficiently. These withdrawals left two bidders in the
competition.
- Having selected GeneSYS as the preferred bidder, the Agency negotiated the
final details of the deal without conceding an increase in price or reallocation
of risks. The preferred bidder stage lasted nearly 10 months, which was five
months below the average for PFI projects that closed between 2004 and 2006
(Figure 9 in the National Audit Office’s report Improving the PFI tendering
process, HC 149, Session 2006-2007). During this stage, GeneSYS’s bid price fell
by £2 million, without changes to the allocation of risks. The outcome of these
negotiations demonstrates that price rises during the preferred bidder stage of
a PPP procurement are not inevitable.
- The tendering phase lasted more than four years, over two years longer than
originally planned and the cost of professional advice at £15.5 million exceeded
the Agency’s estimates by £10 million. There were a number of external events
and major changes in scope that lengthened the timetable. The majority of the
lengthening was due to the Agency’s requirement for high quality contract
documents. As a consequence, the advisers’ costs increased. The frequent
revisions of the budget for the advisers (Appendix 5) suggest that the Agency
struggled to quantify the amount of work needed to complete the procurement.
- At
contract award, the Agency’s estimate of the present value cost of the Public
Sector Comparator (PSC) (£415 million in 2004 prices) was marginally more
expensive than the PPP deal (£385 million in 2004 prices). While negotiating the
deal, the Agency sought to benchmark the cost of the PPP by estimating, in the
PSC, what a conventional procurement might cost. The PSC was designed to produce
a single figure comparison for a given quantity of work and included an upward
adjustment of £85 million for risks. The purpose of the risk adjustment was to
inform the Agency’s decision on whether to pursue a PPP deal or a conventional
procurement for the complex NRTS requirements. In calculating the risk
adjustment for this novel project, and given the inevitable uncertainties, the
Agency relied on the experience and judgement of its advisers. In our view, for
most PPP contracts involving the construction of fixed assets, it is preferable
to provide a range for the costs for the comparator, as opposed to a single
point estimate. We would also expect to see allowances for events turning out
better than expected.
- The new services are now up and running and benefits for road users from
other Agency projects dependent on the NRTS are beginning to be realised. The
upgraded telecommunications systems went live in October 2007. Enhancements to
existing means of communicating with road users are beginning to come on stream
and new means are planned. It is, however, too early to make a full assessment
of operational performance or of the effectiveness of the pre-pricing
arrangements for additional works.
Value for Money Conclusion
- In respect of the value for money of the procurement alone, there are
inevitable uncertainties in the estimated costs of a PSC, but the Agency has
secured, through competition, a PPP with fixed prices and in-built flexibility
for a cost similar to the Agency’s financial estimate of a conventional project.
During the preferred bidder stage, the Agency did not concede either an increase
in price, or reallocation of risks. Unlike conventional procurements, a PPP has
the potential value for money advantage of transferring risks to the private
sector. Some risks have already materialised and have been borne by GeneSYS,
rather than by the taxpayer. The relatively short elapse of time since the new
services went operational in October 2007 precluded collection of sufficient
material for us to judge the value for money of the operational delivery of the
services.
- The overall value for money of the NRTS project depends on how useful the
new telecommunications systems prove to be in relation to the Agency’s
implementation of other projects now enabled by these new systems.
Recommendations
- Encouraging market interest in a PPP project is crucial to the creation of
competitive tension. Some of the Agency’s higher scoring, pre-qualified bidders
did not respond when the Agency re-advertised the project nearly a year after it
had first invited parties to express an interest in bidding. Delaying going to
the market until the scope and structure of a project are clear should result in
a more realistic time table.
- In putting together the PPP deal, the Agency negotiated a range of
contractual terms designed to protect value for money, including the pre-priced
schedule of additional works that the Agency can call off as and when required.
Authorities should always consider carefully whether the expected scale of
future changes to the services they require make a standard PPP contract
suitable. If not, they should consider introducing protections similar to those
negotiated by the Agency for the NRTS.
- Current Treasury guidance recommends that authorities use a public sector
comparator in the early stages of a project to assist in the selection of the
best procurement route. Inevitable uncertainties in pricing a comparator
project, particularly adjustments for risk, mean that authorities should not
rely on a single figure public sector comparator but should consider a range of
values. Public sector comparators should not be used as the sole test of value
for money for a particular procurement route. Instead, authorities should
conduct wider analyses of the costs and benefits of each available procurement
route.
- The procurement team’s preparations for the preferred bidder negotiations
included acquiring extensive knowledge of GeneSYS’s financial model and the
underlying costs. During the competitive phase of the procurement, the Agency
required bidders to submit their financial models and input costs as part of
their bids. Later, the Agency incorporated GeneSYS’s financial model and the
costs into the contract to aid in the evaluation of future changes not covered
by the pre-priced schedule of works. Authorities should follow the Agency’s
example. They should obtain and analyse their bidders’ price build ups, as well
as the bidders’ financial models, to assess the reasonableness of the tendered
prices. Authorities should also ensure that they retain an understanding of the
bases of their contractors’ prices sufficient to test the value for money of any
variations to the services.
- While authorities will always require high quality professional advice to get
good value for money when procuring a PPP deal, it is equally important that
costs are monitored carefully. This is particularly important where a project,
such as the NRTS, undergoes major changes in scope and structure. Authorities
should produce realistic procurement budgets and timetables, especially for the
use of professional advisers and prepare realistic updates for any agreed
changes in project scope.
- During the procurement, the NRTS project experienced two major changes. The
first brought the operation and maintenance of local connections between over
14,000 roadside devices and the national trunk cable network into the scope of
the project. The second transferred some upgrades of the network, which were not
immediately required, out of the proposed initial works and into the call-off
arrangement for pre-priced additional works. While the Agency had justifications
for the changes, the case for change may not be so clear in future PPP projects.
When a project is to undergo major changes in scope, Authorities should formally
evaluate the impact of the changes on the overall value for money of the
project.
- The Agency’s practice of delegating day-to-day management of projects to
advisers meant that we have not been able to access all the information we
required from the Agency in a timely manner. Changes in staff within an
authority and in advisory firms will occur over time and it would be
unacceptable if, in future years, nobody understood the background to the key
characteristics of a PPP deal. Authorities should always have easy access to key
documents and maintain, in-house, a good understanding of the contractual and
operational issues associated with their projects.