The key factors leading to this success included:
Communicating a vision of improvement
Communication and leadership provided by
senior management (paragraph 3.6) was important in ensuring staff buy-in to the
roll-out. Where staff had a positive reaction to the roll-out, this reduced the
risk of a negative impact on customer service.
Consistent leadership, strong governance and close monitoring by a central
project management team
Project management structures and processes
significantly improved as a result of the experience and challenges faced when
rolling out the first 225 offices (paragraphs 3.5–3.9). This included:
- the establishment of a core project management team and a Senior Responsible
Owner;
- a clearer understanding of the roles and responsibilities of key
stakeholders;
- recognised ownership and accountability for the programme by senior
management;
- more structured reporting and decision-making arrangements; and
- stability of the core project management team.
Planning in detail and developing a replicable process
A single replicable
office design and a standard seven-stage estates gateway process for each site
roll-out (paragraph 3.31) allowed costs to be controlled closely.
Change was managed well at sites that learned from previous experience
Local
management had the support of experienced implementation managers. In some areas
local initiatives were also put in place, such as staff shadowing the work of
offices which had been rolled out. Our site visits highlighted that where
appropriate change management processes were put in place at a local level, the
roll-out was delivered effectively and staff felt confident with the new
delivery of services to customers (paragraphs 3.20–3.22).
Using partnering to incentivise contractors to innovate and reduce costs
The
partnering approach adopted from 2003, and in particular the target pricing
method and performance management of contractors (paragraphs 3.33–3.39),
combined with other initiatives to drive down the cost of the programme. It
allowed for an open and non-confrontational environment for contractors to work
with the Department as one team.
Being prepared to learn as the roll-out progressed
As a result of the experience
of the initial phase, Jobcentre Plus undertook a review of the project delivery
arrangements and identified a number of improvement measures (paragraphs 3.5,
3.23). This included the appointment of a works programme manager from the
private sector to assist in making radical changes to the management of the
programme, such as the procurement arrangements and the adoption of a single
standardised design model. This openness to change also allowed the programme to
respond to developments elsewhere in the Department (paragraphs 1.10,
3.26–3.29).
There is scope to build on this in future projects by:
More use of quantitative data on customer volumes and the costs associated with
the estate
When the roll-out was planned Jobcentre Plus had no choice but to use a
locally-driven model to plan the roll-out, but there is now scope to combine
more quantitative volume planning, modelling and use of Geographic Information
Systems to map office locations in relation to their customers in responding to
future policy developments, including the implications of the Employment and
Support Allowance (paragraphs 3.10 and 4.14). Without these there is a risk of
missing opportunities for achieving efficiencies and of delivering an
inconsistent quality of service across the network.
Earlier introduction of centralised planning and management
processes, and a standardised design approach
At the beginning of the programme, detailed planning of the roll-out
was delegated to local districts. Districts were considered best placed to
understand the requirements of the service in their areas and the condition and
configuration of the estate. A year into the roll-out; the core project
management team concluded, however, that it needed more control over the
direction of the programme to ensure the roll-out was completed to time and
budget. The move to more centralised planning and management processes, in
partnership with the introduction of more prescriptive design guidance, was
effective, while some offices in districts which were rolled out early have
subsequently been closed (paragraphs 2.3, 3.10–3.14).
Finding out in advance what is important to customers and building in
ways of measuring improvements
Customers reacted favourably to the transformed office environment, but
other aspects of service, some of which were also changed by the roll-out, were
more important to them (paragraphs 4.6–4.12). Tracking progress in achieving
non-financial benefits such as changes in customer service would have identified
where benefits were not being achieved, allowed local targets and a better
understanding of what improvements the new network has delivered (paragraph 3.25).