The Major Projects Report 2008 covers cost, time and performance
[Footnote 1] data
for military equipment projects in the year ended 31 March 2008.
For the main report, we examined [Footnote 2] 20 of the
largest projects (shown in Figure 3 on page 8), where the main
investment decision has been taken by the Ministry of Defence (the
Department). The Report also covers ten projects, which are still
in the Assessment Phase, where the main investment decision has not
yet been taken (only limited performance data is reported for these
projects, which are detailed in Appendix 2). Six projects are new
to this year’s Report. Future Lynx, Modernised Target Acquisition
Designation Sight/Pilots Night Vision Sensor, Naval Extremely High
Frequency/Super High Frequency Satellite Communication Terminals
and Typhoon Future Capability Programme projects are all new in the
post-main investment decision population, as well as the Advanced
Jet Trainer project, which has previously featured as an Assessment
Phase project. Project Eagle, to upgrade the mission system of the
E-3D Sentry aircraft, is new in the Assessment Phase project
population. Project Summary Sheets, on which our analysis is based,
are compiled by the Department and summarise progress to date for
each of the 30 projects. These are contained in Volume II of this
Report.