This report focuses on the failure of Metronet and the ability
of the various public sector bodies to manage risk within the PPP
framework. It concludes that at the heart of Metronet’s fate lie
problems of internal governance. It also highlights the key
limitations facing DfT and London Underground in managing risk. The
recommendations focus on improvements in governance, co-ordination,
and assurance on costs as DfT and its partners seek a lasting
solution to the problems of the Metronet PPP contracts.
Recommendations B, C and E would require the agreement of the
Mayor. These recommendations could usefully also be applied to the
management of the Tube Lines contract, although Recommendation E
would require Tube Lines’ consent.
- The five shareholders in Metronet, each with different
interests, chose to structure the business as a joint venture in
which many decisions needed to be agreed unanimously. The
shareholders were also suppliers in a tied supply chain, and they
adopted governance and management structures which gave power to
the suppliers rather than the management of the business.
Metronet’s management was unable to extract key information or
incentivise suppliers to perform their roles in line with its own
interests.
DfT designed the PPP contracts in accordance with the HM Treasury
guidance that existed at the time. HM Treasury’s
Standardisation of PFI Contracts now provides guidance to
Departments on how to achieve commercially balanced contracts,
which avoid the conflicts of interest that can occur when suppliers
have too much influence over what is to be delivered, and how to
achieve value for money. In line with the guidance, future PPP
contracts should be awarded to bodies which have clear leadership,
a credible corporate governance structure and an approach to
securing suppliers which can be demonstrated to be value for money.
Departments also need to ensure:
- contracts with the supply chain are structured to enable those
managing delivery to access the information they need;
- incentives in the contracts and sub-contracts within the supply
chain are aligned with and reflect the interests of the public
sector partner; and
- there is a public sector option to withhold payment unless the
private sector is able to produce reliable and timely records to
back up claims.
Risk management
- The modernisation programme was the responsibility of
the Mayor of London, TfL and London Underground. DfT was not a
party to the PPP contracts, and therefore had no direct visibility
of performance. DfT thus relied to a great degree on due diligence
and monitoring work carried out by Metronet’s shareholders and
lenders to protect their respective investments, and on London
Underground as the contract manager to ensure performance and
delivery.
To understand and manage the risks to which it is exposed, DfT
should:
- collect and analyse a range of financial and performance data
held by parties to the contract or available independently;
- request regular risk reports from London Underground and TfL as
the contracted clients; and
- review the devolved body’s understanding of the key risks to
the project to allow DfT to identify and investigate any issues
relevant to the management of its own risk.
Alignment of interest and governance
A feature of our findings has been the lack of a common agenda
between the various public sector bodies involved, and between
public and private sector. The interests of these bodies need to be
better aligned. We make two specific recommendations:
- DfT was exposed to risk but lacked direct ways of
gaining assurance over the management of this risk.
In the permanent solution for Metronet’s business, DfT should
work with the Mayor of London and TfL to ensure that there are
effective controls to contain costs within agreed limits and to
maximise the value for money of the grant funding it provides.
Effective independent scrutiny and evaluation of London
Underground’s management of major infrastructure projects, on
behalf of both TfL and DfT, could provide greater assurance on
value for money.
- London Underground had limited ability to manage the
contract in a way that prevented costs from escalating. It sought
to undertake rigorous cost analysis as far as possible, but could
have drawn more on the Arbiter as a source of information and cost
assurance. As the party responsible for managing
performance under the contracts, London Underground should have
sufficiently detailed information available to it to confirm that
work is affordable, within the limits of the grant, and that the
taxpayer is receiving value for money. But under the contracts,
London Underground needed to ask the Arbiter formally when it
needed more detailed cost and performance information. The Arbiter
should, within the statutory framework, work with London
Underground to provide assurance on whether the work performed is
affordable and value for money. This assurance could be achieved by
the type of high‑level benchmarking exercises undertaken by the
Arbiter to compare the performance of PPP suppliers with other
companies carrying out similar activities. This top‑down assurance
should then be supplemented by more detailed analysis of individual
components of cost where this would enable better management of the
contract by London Underground.
The role of the Arbiter
- Early provision of information about the likely extent
of economic and efficient additional spending by Metronet would
have helped the public sector manage the risks better, although
this alone would not have been sufficient to ensure value for
money. The PPP Arbiter was the external party with greatest access
to Metronet’s performance data and could therefore have been
invited to give early warning on the cost implications of its
delivery problems. London Underground, as contract manager, did not
have access to the same level of information.
To enable the Arbiter to highlight issues affecting the
taxpayer’s interests and continue to monitor Tube Lines
effectively, any permanent solution should allow effective
comparison to be made with Tube Lines and give the Arbiter
oversight over the comparator.
Any new oversight arrangements should be clear about roles and
responsibilities and should:
- allow DfT, which has the greatest financial risk but is not a
party to the contracts, to request investigations where
appropriate;
- require an annual review, including an audit of financial
models produced, to improve the transparency of information about
delays or cost overruns and make DfT aware of any risk to the
taxpayer; and
- allow an Extraordinary Review or other investigation where it
is possible that the public sector may have to provide extra
finance, even where it has not been requested by other
parties.
It is desirable that new measures adopted to protect the public
interest should also apply to the Tube Lines contracts, which would
improve DfT’s ability to understand and manage risk. Any new
arrangements would, however, require the agreement of Tube Lines
and London Underground under the remaining PPP contract.
Whole life costing
- The Joint Steering Committee has considered a range of
options for the line upgrades, rolling stock, station maintenance
and renewals work that were expected to be undertaken by Metronet.
While the permanent solution is under consideration by the
Secretary of State and the Mayor of London, TfL is determining
Metronet’s budgets annually.
A permanent solution should be based on a whole life costing of
infrastructure renewal and avoid a return to short-term budgeting
based on annual grants from DfT. The long-term funding agreement
between DfT and TfL provides the necessary framework. TfL seeks to
adopt the principles of a whole life approach to asset management
in its business plan. A TfL business plan published in November
2008 for the period to 2018 is under consideration and needs to be
taken to a conclusion if infrastructure renewal is to reflect
strategic priorities rather than ‘patch and mend’.