National Audit Office Value for Money Report: Executive Summary
Central government’s use of consultants
Executive summary
- Consultants, when used correctly and in the
appropriate circumstances, can provide great benefit
to clients – achieving things that clients do not have
the capacity or capability to do themselves. On the
other hand, when used incorrectly, consultants can
drain budgets very quickly, with little or no productive
results. For the purpose of this report we have defined
‘consulting’ as always having two characteristics. First,
individuals or companies are engaged to work on
specific projects that are outside the client’s business as
usual, and there is an end point for their involvement.
Second, responsibility for the final outcome of the
project (for example achieving cost savings or improving
quality of service) largely rests with the client. As
such, consulting is distinct from ‘outsourcing’ or ‘staff
substitution’. For example the Cabinet Office used
consultants to help develop the Capability Review
programme[Footnote 1] and the Home Office used consultants to
get advice on procurement for the eBorders programme[Footnote 2].
- The table of key data below shows
central government spent £1.8 billion on consulting in
2005-06 which is more than previously reported.
The table also shows a decline in spending by central
government, from a high of £2 billion in 2003-04, which
can be attributed to three departments3 rather than a
wider trend. We estimate that spend across the Public
Sector increased by 33 per cent between 2003-04 and
2005-06, taking it up to £2.8 billion, largely due to a rise
in spending in the National Health Service.
- It is not possible to make an overall assessment of
the benefits that have arisen from the money spent on
consultants, in part because departments rarely collect any
information on what has been achieved. In any case there
are significant challenges in assessing value for money
from consulting projects. For example it can be hard to
identify useful measures that are suitable for all types of
projects and attributing cause and effect is not always
easy, even where performance has improved.
- There are examples where consultants have added
real value and enabled departments to make improvements
they would not have otherwise. For example the Ministry
of Defence is saving on its procurement having used
consultants to help implement a new approach and
develop internal procurement capabilities. Nevertheless
we conclude that, while there have been some important
improvements in using consultants, for example procuring
them more economically and efficiently by using framework
agreements[Footnote 4], there is some way to go before central
government overall is achieving good value for money
from its use of consultants. Furthermore, the Treasury has
indicated in the Pre-Budget Report 2006 that “Government
will continue to drive value for money” in this area[Footnote 5].
The basis for our value for money assessment is the lack
of progress we found in implementing good practice as
recommended by the Committee of Public Accounts[Footnote 6],
the National Audit Office[Footnote 7], and the Office of Government
Commerce[Footnote 8]. More specifically, based on our detailed review
of five departments (Figure 2 below)[Footnote 9] (including the
review of individual consultancy projects) and OGC, we
have found that, for the most part, departments:
- do not collect and aggregate adequate
management information on their use of
consultants (such as types of services purchased and
procurement route used) to better understand over
time their use of consultants and the benefits they
bring. OGC has collected spend information on
consultants in the past as part of an exercise looking
at government expenditure. However this activity
is no longer carried out as the information received
from departments was inconsistent and incomplete,
diminishing the value of the exercise. OGC makes
available to departments financial, contract and
strategy information on key consulting suppliers[Footnote 10].
- do not make proper assessment of whether internal
resources could be used instead through taking a
medium to long term view to the division of work
between internal and external resources. This strategic
view will help them plan their recruitment and
training, as well as their use of consultants (including
the skills that should be transferred to internal staff).
The Ministry of Defence, for example, has a relatively
well-developed process for comparing using internal
staff versus consultants on projects. As an illustrative
example, the average daily cost of a Ministry of
Defence internal consultant is £550 and an external consultant is £1,245[Footnote 11].
- do not have adequate controls on awarding contracts by single tender which means departments
do not get the benefits of competition such as better prices and a broader range of ideas;
- do not undertake and share post-project performance reviews to inform future buying
decisions. The performance of consultants is not
regularly assessed and the information is not shared amongst buyers in the department;
- do not actively engage with and manage the
relationships with key consultancy suppliers to better
understand how they work and align objectives. Most
departments do not know all the consultancy projects
that are done by their key consultancies within their
department. Departments also need to be aware that
consultants may tend to target public sector business
when there is a downturn in their private sector income (Figure 1e).
- do not regularly plan for and carry out the transfer
of skills from consultants to internal staff to build
internal capabilities. Although the transfer of skills is
often encouraged in departmental guidance, it is not
consistently carried out by project teams.
- In other areas many departments have made
better progress:
- the involvement of procurement staff in the buying
process to provide commercial expertise and enforce
organisational policies on procurement. For example,
at the Department for Communities and Local
Government procurement staff review the business
cases for all consulting projects.
- the use of framework agreements. SummARy
The use
of framework agreements generally reduces
procurement costs and provides better prices.
Departments are making good use of framework
agreements. For example in 2005-06, the Cabinet
Office used framework agreements for 85 per cent
of spend on consultants. Thirty four per cent of total
central government spend in 2005-06 on consultants
went through OGCbuying.solutions framework
agreements. OGCbuying.solutions has estimated
that its consultancy framework agreements have
generated savings of £111 million in 2005-06 based
on the £740 million that was spent through these agreements across the public sector.



Recommendations
- Our analysis has identified a number of areas
where central government (and indeed the wider public
sector), guided by OGC, can improve the way they
assess the need for, procure and use consultants. These
recommendations will help reduce costs further and
improve the effectiveness of consultancy projects. We
consider that annual efficiency gains (achieving the same
results by spending less or better results by spending
the same) in the region of 15 per cent in the first year,
rising to 30 per cent by the third year can be made by
central government. These gains are estimated after taking
account of the investment costs, for example of enhancing
the internal skill base[Footnote 12]. To improve value for money we
highlight seven priority areas below.
- Public bodies need to be much better at identifying
where core skill gaps exist in relation to medium
and long term programme requirements. This
knowledge should be used to plan for recruitment,
training, and using consultants. Recruitment of
full-time personnel and training of existing personnel
can provide better value for money than continued
use of consultants. The external recruitment process
and structures (such as salary bands) need to provide
public bodies with a genuine alternative to using
consultants[Footnote 13]. Public bodies should do more to define
and measure the transfer of skills[Footnote 14] from consultants
to internal staff as this will reduce future reliance
on them by increasing internal core capabilities.
There is an important connection to be made
between this need for strategic resource planning,
and the Capability Review and Professional Skills for
Government initiatives.
- Public bodies should start with the presumption
that their own staff are best fitted for their
requirements. While it will often be the case that
they need to purchase specific expertise from
consulting firms[Footnote 15], more generalist requirements can
be met more cost-effectively by internal resources.
Public bodies need to have improved mechanisms
to find appropriately skilled internal staff (from
within the organisation or from other public bodies),
understand the costs of internal staff, and make
firm commitments to resource these posts on time.
Internal staff should hold key programme roles to
ensure that the public body maintains accountability
and control of the work. Michael A. Noll (professor
at Annenberg School for Communications at
University of Southern California) has commented
that, “[Customers] are afraid to stick [their] neck out
…you are punished if you are wrong, so you don’t
want to do that… The net result of this is the fear
of making a mistake. So bring in the consultants…
We are just doing what [the consulting firm]
suggested.”[Footnote 16] OGC should look to incorporate
the review of how key project roles are allocated
between internal staff and consultants into the OGC
Gateway Review process.
- Public bodies should adhere to OGC guidance
on the recommended threshold levels requiring
Ministerial or Permanent Secretary approval of
consultancy contracts. Guidance on approval levels
was issued by OGC in 2002 and then re-issued in
March 2006[Footnote 17]. Public bodies should ensure that
this guidance is communicated throughout their
organisation and enforced, with regular compliance
checks performed. Approvals should be based on
a robust business case. Adhering to the guidance
will ensure that senior management has full sight
of the larger consulting contracts, promoting better
accountability for this spend.
- Public bodies need to engage with the market
earlier to explore a range of possible approaches
and contracting methods. Early contact with
suppliers during the procurement process improves
both the supplier and client’s understanding of the
requirement. Public bodies would get more tailored
and innovative responses to their invitations to
tender. OGC should communicate the good practice
on early supplier/client discussions to make public
bodies aware of what can and cannot be done under
European Union procurement rules.
- Public bodies should make more use of different
payment mechanisms such as fixed price and
incentivised contracts instead of the standard time
and materials. Different payment mechanisms can
help control costs and formalise the joint objectives
between clients and consultants. The different
payment options require a strong understanding of
the project’s objectives, scope, risks, and approach.
For example, in fixed price arrangements, public
bodies need to be clear on how to deal with changes
to scope; in incentivised ones, they may need to
incorporate potential price variations into their
financial planning. OGC can help public bodies
by developing and communicating its guidance on
the conditions when fixed price and incentivised
contracting are appropriate.
- Public bodies must be smarter when it comes to
understanding how consulting firms operate and
in sharing information about their performance. Public bodies should have regular, senior-level
discussions with their consultants to openly discuss
medium to long-term objectives and plans. Public
bodies should also use their understanding of
suppliers’ objectives to maximise their purchasing
advantage. Public bodies need to have a clear
understanding of who their key suppliers are,
how they are organised (such as the archetypal
consulting firm’s pyramid structure[Footnote 18]), their
incentive mechanisms (which might focus on
selling further work), and commercial practices. For
example, consulting firms may obtain travel and
accommodation rebates while working on client
projects and public bodies need to be more astute
to ensure that these rebates are shared. Public
bodies should collect and share information on
the performance of consultants to inform buying
decisions. OGC should work with public bodies to
identify key information and then look to aggregate
this information to provide a pan-government view.
OGC can also aid public bodies by communicating
guidance on managing suppliers, market
intelligence, and co-ordinating cross-government
supplier meetings to help the government act as a
single customer to its key consultants.
- Public bodies need to provide sufficient incentive
to staff to make the consultancy project a success. Recent research[Footnote 19] has shown that the further removed
someone is from the decision to use consultants the
more likely they are to feel confused about project
responsibilities and accountabilities, frustrated because
they don’t know what the consultants are doing,
complain of poor communication and be cynical
about the consultants involvement. “Supporting
Paper I – Building client and consultant commitment”
highlights how public sector organisations can work
most effectively with consultants and makes practical
recommendations for public sector managers involved
in consulting projects.
- Public bodies need to be much better at identifying
where core skill gaps exist in relation to medium
and long term programme requirements. This
knowledge should be used to plan for recruitment,
training, and using consultants. Recruitment of
full-time personnel and training of existing personnel
can provide better value for money than continued
use of consultants. The external recruitment process
and structures (such as salary bands) need to provide
public bodies with a genuine alternative to using
consultants[Footnote 13]. Public bodies should do more to define
and measure the transfer of skills[Footnote 14] from consultants
to internal staff as this will reduce future reliance
on them by increasing internal core capabilities.
There is an important connection to be made
between this need for strategic resource planning,
and the Capability Review and Professional Skills for
Government initiatives.
- [back] The Reviews consider capability in the Civil Service in three key areas – leadership, strategy and delivery and aim to identify where departments need to improve.
- [back] The eBorders programme is looking to deliver timely data, information, intelligence and risk assessments to relevant government agencies on all passengers seeking to enter or leave the UK.
- [back] Department for Work and Pensions, Department for Trade and Industry, Ministry of Defence.
- [back] A framework agreement is a general term for agreements with providers which set out terms and conditions under which specific purchases (call-offs) can be made throughout the term of the agreement.
- [back] Pre-Budget Report 2006, paragraph 6.30.
- [back] Better Value for Money from Professional Services (2002).
- [back] Purchasing Professional Services (HC 400, 2001).
- [back] Delivering World Class Consultancy – A Statement of Best Practice (2002). OGC distributed this guidance on the use of consultants in 2002, however the impact of the guidance was not quantified. OGC is now communicating an updated version. OGC is an independent Office of the Treasury reporting to the Chief Secretary of the Treasury. It is responsible for a wide-ranging programme which focuses on improving the efficiency and effectiveness of public sector procurement.
- [back] Part Three and Appendix 1 provide a full assessment of progress in our case study departments.
- [back] Six suppliers are currently regarded as key consultancy suppliers: Deloitte, KPMG, PWC, PA Consulting, Hedra and Tribal.
- [back] The Ministry of Defence internal consultant average daily rate assumes 150 working days in a year and includes direct and indirect staff costs (for example pension costs, provision of IT, rent and property management) and an overhead to cover strategic support to the consultancy practice. It does not include the cost of travel and subsistence. The external consultant cost is the benchmark average of a management/business consultant from a study commissioned by OGCbuying.solutions and undertaken by 4C Associates into consultancy pricing across the public sector in February 2005. The benchmark does not reflect OGCbuying.solutions S-Cat pricing.
- [back] Further information on the potential efficiency gains is detailed in Supporting paper III – Methodology.
- [back] “Departments may offer starting salaries above the Progression Target Rate when, in seeking to recruit externally, they consider that the Progression Target Rate does not allow them to attract candidates with the necessary skills. In these cases departments may agree a rate for the job with the Cabinet Office in the light of market evidence”, Review Body on Senior Salaries 28th Report on Senior Salaries 2006 (Cm 6727, March 2006), paragraph 2.9.
- [back] For the purpose of this report the transfer of skills (skills transfer) also includes the transfer of knowledge (knowledge transfer).
- [back] In cases where the department’s requirements are met by individual consultants rather than teams, some of the benefits of engaging a consulting team (such as the quality assurance provided by more senior consultants) may not be included.
- [back] Dangerous Company, James O’Shea and Charles Madigan (1997), Nicholas Brealey Publishing, p. 9.
- [back] OGC guidance states that Ministerial or Permanent Secretary approval is required at the tendering stage in respect of: (1) all non-competitive procurements of any external professional service with a likely value in excess of £50,000; (2) all competitive procurements of any external professional service with a likely value in excess of £250,000.
- [back] In a typical pyramid structure, the expensive time of a small number of people at the apex of the pyramid is spread across a large number of projects which are run by experienced project managers and staffed with more junior, less experienced consultants.
- [back] Source: Ensuring Sustainable Value from Consultants, Management Consultancies Association, 2006.
National Audit Office, 151 Buckingham Palace Road, Victoria, London SW1W 9SS
Switchboard: +44 (0)20 7798 7000 / General enquiries: +44 (0)20 7798 7264 / Press enquiries: +44 (0)20 7798 7400
To comment on the site, please use our
Feedback form
