National Audit Office Value for Money Report: Executive Summary
Preparations for the London 2012 Olympic and Paralympic Games – Risk assessment and management
Summary
- This is the first in a series of National Audit Office
reports on the preparations for hosting the London 2012
Olympic and Paralympic Games. It is an early look at
the progress that has been made to put in place the
necessary delivery and financial arrangements since
London was chosen as the host city on 6 July 2005.
In most areas the arrangements are still being developed
or are bedding down, and the report therefore identifies
key risks and challenges going forward.
- In future reports we will examine how the delivery
and financial arrangements are working in practice and
track progress in preparing for the Games. In addition,
we will be reviewing the work to establish the budget for
the Olympic programme, with a view to reporting our
findings when the budget has been finalised.
- Our main findings are as follows.
- Progress has been made in putting in place the key
delivery structures, including setting up the Olympic
Delivery Authority, the London Organising Committee
of the Olympic Games and Paralympic Games
(LOCOG), and the Olympic Lottery Distributor, and
work is ongoing to develop underpinning practices
and procedures. The delivery structures are complex,
however, and this does bring the risk of cumbersome
decision making.
- The layout of the Olympic Park has been finalised,
nearly all the land has been acquired, and work on
the physical site is underway. The Olympic Delivery
Authority has published a draft Transport Plan for
consultation and is preparing the Olympic planning
applications. Work is also ongoing to finalise
proposals for the legacy use and ownership of the
venues, and to develop plans for delivering and
measuring the wider benefits of the Games, a key
driver behind London’s bid.
- There has been a good deal of work on the cost
estimates for the Olympic venues, associated
infrastructure and other non-staging costs.
In November 2006 the Secretary of State for Culture,
Media and Sport reported that, although some
offsetting savings have been identified, overall
the cost estimates for the the Olympic Park have
increased by some £900 million. A number of areas
of uncertainty remain and there continues to be no
final agreed budget, with implications for budgetary
planning and control. Substantial further public
funding is likely to be required in addition to the
public sector funding package of £2.375 billion
that was agreed before the bid. The Government
is also to provide £1.044 billion towards the costs
of infrastructure on the site of the Olympic Park.
LOCOG has a budget of £2 billion for staging the
Games. As required by the International Olympic
Committee, the Government has underwritten the
costs of the Games.
- Across the Olympic programme as a whole, the
Olympic Programme Support Unit has been set
up to track progress and key risks, and provide the
Olympic Board with the information it needs to
make decisions. Within central government, the
Government Olympic Executive will play a key
role in co-ordinating the various contributions that
government departments will make to the Games
and in overseeing the Olympic Delivery Authority,
LOCOG and the Olympic Lottery Distributor.
- Progress has been made in putting in place the key
delivery structures, including setting up the Olympic
Delivery Authority, the London Organising Committee
of the Olympic Games and Paralympic Games
(LOCOG), and the Olympic Lottery Distributor, and
work is ongoing to develop underpinning practices
and procedures. The delivery structures are complex,
however, and this does bring the risk of cumbersome
decision making.
- Our overall conclusion is that the key relationships
and working arrangements to deliver the Olympic
programme are still being developed. There are a number
of areas of risk that will need to be managed but a major
risk is the lack of final agreed cost estimates and an
accompanying funding package, and this will inevitably
have a detrimental impact on the programme if it is
allowed to continue.
Recommendations
- The main areas of risk that need to be managed
for the successful delivery of the Games are set out in
Figure 1. The risks are, of course, interdependent – failure
in any one area will impinge on others. At the end of
each section of the report are boxes setting out what
we see as the key actions required to manage the risks.
These points do not imply a lack of attention on the part
of those involved; indeed much has been done and is
being done. Nevertheless, with 18 months of the timetable
of 84 months now elapsed, it is essential to keep the
momentum up so that progress is maintained.
