Skip navigation | Accessibility and accesskey details | Sitemap

National Audit Office Value for Money Report: Executive Summary

Building and maintaining river and coastal flood defences in England

Summary

  1. Around 469,000 households and businesses in England are at significant risk of flooding. Flooding can damage property and belongings, and any householders affected face the stress and inconvenience of having to move into temporary accommodation while their home is cleaned, allowed to dry out and repaired.[Footnote 1]The cost of flooding will depend on the scale of damage and nature of the property, but existing research suggests that flood repairs can be up to £40,000 per household.
     
  2. The Environment Agency expects the risks of flooding are likely to rise significantly over the next century as a result of, for example, climate change and the building of new houses. [Footnote 2] The Environment Agency (the Agency) is responsible for managing the risk of flooding from “main” rivers and the sea in England and Wales. [Footnote 3] The Agency’s functions include the construction of new flood defences (£162 million in 2006-07), the maintenance and operation of existing flood defences (£176 million), as well as raising public awareness of the dangers of flooding and responding when such incidents arise (£39 million). The Agency has developed information and warning systems so that the public can determine whether their property is liable to flooding and register to receive automated advance warnings if a flood is likely to occur. Minimising the financial cost of flooding, however, largely depends upon the effectiveness of the flood defences, and this report focuses on the Agency’s construction of new flood defences and the maintenance of 24,000 miles of flood defences and 46,000 flood defence structures.
     
  3. At the time of our last report on flood defences in 2001[Footnote 4], 20 regional and local flood defence committees were responsible for overseeing the management of flood defences in England. Since then, the numbers have been streamlined to 11 regional committees and funding arrangements have changed so that the Environment Agency now receives a single grant-in-aid from the Department for Environment, Food and Rural Affairs (the Department) to allocate to the committees. Whilst the 11 flood defence committees still have a formal role in flood risk management in their local area, the Agency has started to recommend priorities to them on the basis of needs nationally. The Agency has also taken over responsibility for the management of critical ordinary watercourses from local authorities and internal drainage boards, and the Department is considering whether the Agency should also take on a greater role in coastal protection from local government. The key improvements in performance we identified during our examination were:
  1. Building on this progress, this report sets out those areas where there is room for further improvements in the Agency’s value for money performance. The Committee of Public Accounts’ previous report on flood risk management in 2001 concluded that complex organisational arrangements had led to inconsistent service levels across England.[Footnote 5] Although the arrangements have been simplified, levels of expenditure on locally managed construction and maintenance work continue to vary across the country and do not yet adequately reflect the risk of flooding in each region. In addition, there may be an imbalance between the Agency’s focus on the construction of new flood defences and its maintenance of existing assets. The Agency has not met its target to maintain 63 per cent of flood defence systems in target condition; and the Agency estimates that only 57 per cent of all systems and 46 per cent of high risk systems, such as those protecting urban areas, are in their target condition, with consequent risks should a flood occur.[Footnote 6] In practice, however, the Agency’s investigation of the autumn 2000 floods found that instances of flood defences failing were rare (less than one per cent of flooding was due to such instances).[Footnote 7] Until the Agency develops more comprehensive data on the typical lifespan and maintenance costs of its assets, it is difficult to establish future resource requirements accurately, although the Agency has estimated that it requires an additional £150 million a year. In the meantime, there is scope to improve cost-effectiveness and thus reduce any additional funding that may be required.
     
  2. To improve cost-effectiveness, the Agency needs to address:

  3.  
  4. We recommend that the Agency:

    i) Focuses attention more consistently on the maintenance of those flood defences which are considered to be medium or high risk. Area managers should develop maintenance strategies and work programmes to reflect this approach.

    ii) Implements a national management policy for dealing with third party assets. Whilst the Agency may not have the authority to enforce repairs, the Agency should nevertheless bring such defects to the attention of the landowner or third party. The strategy should include a risk-based approach of writing to landowners or other third parties to highlight any significant deficiencies identified during inspection, the consequent risk to neighbouring land and property, and what actions they consider are necessary.

    iii) Draws upon the findings of the planned benchmarking exercise to generate real maintenance efficiency savings by applying good practice from similar public and private sector organisations and from within the Agency’s areas and regions more widely across the Agency.

    iv) Introduces the planned improvements to training for staff involved in maintenance and emergency response during 2007. Regional managers should incorporate a minimum training requirement into staff objectives to monitor and encourage attendance on suitable training courses.

    v) Conducts a review in accordance with OGC good practice at the end of each major project to determine whether benefits were realised and identify any lessons learned. The extent of each review should be tailored to the size and nature of the associated scheme, and the results held centrally so that they are accessible by other areas and regions.

    vi) Streamlines its approval process so that detailed plans are not commissioned until the proposed project has been through a simplified gateway review and work is likely to start within, for example, the next two to three years, drawing on the current project by the Agency to reduce the costs of project development.

    vii) Make improvements to the computer asset database, in particular to:

    • Assess the long term suitability of the current computer database and if applicable, set out a timetable for the possible development of a replacement, drawing on the outcome of its current review;
       
    • Improve its suite of reports which can be run nationally from the asset database each month to monitor progress by areas and regions in improving the condition of high and medium risk systems, improving data quality and completing inspections;
       
    • Improve the quality and usability of data on asset management by delivering its targets for areas to include all information on the database, and including a cross reference on each inspection report to confirm that the remedial work has been done and where the paper based record can be found;
       
    • Confirm that, following inspections, key remedial works identified have been completed satisfactorily, applying a risk-based approach so that more significant defects are followed up by inspectors, while more minor works can be checked by the maintenance manager on site.

  1. [back] National Flood Risk Assessment 2006 Results – Headline Figures, Environment Agency, January 2007.
  2. [back] Financial Costs of Property Damages, The Halifax Dundee Flood Loss Tables 2005, Dundee University and HBOS, 2005.
  3. [back] While we refer to the Agency as responsible for flood risk management in England, it actually has permissive powers, under the Water Resources Act 1991, to manage flood risk arising from designated “main” rivers and the sea. This report focuses on the Agency’s work in England as the Wales Audit Office plans to report separately to the Welsh Assembly on the Agency’s performance in Wales.
  4. [back] Inland Flood Defence, HC 299, 2000-01, March 2001.
  5. [back] Inland Flood Defence, HC 299, 2000-01, March 2001.
  6. [back] The Agency assesses flood risk management systems as high, medium or low consequence based on a combination of the potential impact of flooding on people and the impact of flooding on property, as set out in Figure 25. This is only one part of flood risk related to assets, the probability of failure of the assets in a system being the other. Reports from the asset database suggested that the proportion of high risk systems at their target condition was 35 per cent and the proportion of all systems at their target condition was 46 per cent. These figures were obtained from an average of two separate reports, one identifying the number of systems which pass on the basis of flood defence structures alone, and one identifying the number of systems which pass based on their linear defences alone. The Agency has advised us that, as a result of the database not yet being fully populated with area office data in the correct format and the problems with reporting we have described, the information obtained from area managers, which we quote in paragraph 4, was a more accurate reflection of asset system conditions at the time of our report.
  7. [back] Lessons learned Autumn 2000 floods, Environment Agency, March 2001.
  8. [back] Inland Flood Defence, HC 299, 2000-01, March 2001.