National Audit Office Value for Money Report: Executive Summary
Coal Health Compensation Schemes
Summary
- In January 1998 the Department of Trade and
Industry, restructured and renamed in June 2007 the
Department for Business, Enterprise and Regulatory
Reform (the Department), took over responsibility for
the accumulated personal injury liabilities of the British
Coal Corporation (the Corporation). The High Court
found the Corporation negligent in January 1998 in
respect of lung disease caused by coal dust, known as
Chronic Obstructive Pulmonary Disease (COPD). And in
July 1998 the Court of Appeal confirmed an earlier High
Court decision of negligence in respect of hand injuries
caused as a result of using vibrating equipment, known
as Vibration White Finger (VWF).
- The Department, in negotiation with the Claimants
Solicitors’ Groups[Footnote 1] and subject to the approval of the
High Court, introduced two schemes, one for COPD and
one for VWF, to compensate former miners. Potential
claimants could make applications for compensation via
their legal representative. The Department contracted
initially with IRISC, and since 2004 Capita Insurance
Services, to administer and assess claims. It also
contracted with independent medical assessors to carry
out medical examinations. The Department met the cost
of the claimant’s legal representation, where these claims
were successful.
- The two schemes remain under the jurisdiction of
the High Court in England and Wales, which continues to
require regular updates of progress, usually around three
times a year. The Court also continues to rule on matters
where the claimant and the Department cannot agree.
- By March 2007 the Department had received over
591,000 COPD claims and 169,000 VWF claims. These
greatly exceeded its initial forecasts of 173,500 and
45,000 respectively and it had to increase significantly the
resources applied to process applications as the schemes
evolved. Difficulties in dealing with the number of claims
and the complexities posed by some of them also led to
long delays in paying compensation for some claimants.
By the end of March 2007, just over 168,000 COPD
claims and 27,000 VWF claims remained outstanding; the
median settlement under the COPD scheme was around
£1,500, taking some 29 months to process claims; and
for the VWF scheme £8,300, and some 20 months.[Footnote 2] The
median settlement for COPD claims reflects the fact that
settlements are discounted to take account of the effects of
smoking and impairment caused by normal levels of dust
in the air, for which the Corporation was not responsible.
- In 2005, the Department set a target to achieve
effective closure to processing VWF claims by
31 October 2007 and COPD claims by 16 February 2009.
When all the claims are settled the Department expects to
have paid some £4.1 billion in compensation. It is also likely
to have spent some £2.3 billion in administration costs, in
the form of payments to miners’ legal representatives, the
cost of its contractors[Footnote 3] and its own legal costs.
Overall conclusion and main findings
- The Department always faced a formidable challenge
in establishing two schemes on this scale to compensate
people who were often elderly, ill, and anxious to receive
the compensation rightfully due to them. The schemes were
large and raised challenging issues reflecting the complexity
of the coal industry, the nature of the illnesses involved, and
the long time period over which the Corporation had been
found negligent. The task was significantly complicated by
the common law nature of the schemes where each rule and
procedure must be negotiated with the claimants’ solicitors
and where any differences of opinion are resolved through
the courts. From the start, the Department was under
pressure from all parties to get the schemes up and running.
- When the final claims have been discharged the
Department will have settled more than three quarters
of a million cases. This would be in itself a major
achievement, but the Department might have been able
to deliver the schemes more quickly and more costeffectively
had it been better prepared at the time of
the Court rulings and more particularly in the period
of transition of responsibility from the Corporation. The
Department produced limited strategic oversight or
forward planning on how it would handle any resulting
liability and insufficient resource was allocated to the task.
This lack of preparation was to make the Department’s
task significantly more difficult to administer, require
substantial effort to put right, and cause frustration and
upset to some claimants. These schemes illustrate vital
lessons that should be learned should Government
departments be required to establish other compensation
schemes in the future.
- When developing the schemes, the Department
relied primarily on Corporation estimates until 2001.
These estimates significantly underestimated the number of
potential claimants. They also failed to recognise that the
liability would include claims on behalf of the estates of
deceased miners, not just widows. An actuarial assessment
at the time the schemes were being developed would have
helped identify where the uncertainties lay and would have
allowed these to be taken into account when designing
and negotiating the details of the schemes. However,
as the Department’s 2001 review of the assumptions
underlying the estimates on COPD demonstrated, the
spectrum of results is likely to have been very broad, still
giving rise to considerable uncertainty.
- The Department set out to pay compensation
without a systematic in-depth option appraisal being
considered at more senior levels within the Department.
There is evidence that some options were considered
at working level, for example the possibility of putting
the schemes on a statutory footing, but by the time of
the court judgements the range of options open to it had
already narrowed significantly. Also, in order to ensure
equity between claimants, combined with the need
to negotiate with parties representing claimants, the
Department made the process complex without testing
the practical implications of the rules being drawn up,
particularly where the amounts of compensation might
be small.
- Once the scale of the problems began to become
clear, the Department took action to address the challenges
posed. In 2001 it brought in a senior secondee with
experience of programme management. It improved
strategic oversight and programme management; recruited a
broader range of skills onto its team; and further work with
contractors, such as the computerisation of some records,
helped to speed up processing and deliver efficiency gains.
In 2004, as part of a wider study of risk management
in government, the National Audit Office[Footnote 4] found that
the Coal Liabilities Unit had demonstrated effective risk
management, making it an integral part of day-to-day
project management and communication with all parties.
- It has taken years of intensive effort for the
Department and its contractors to get to a position where
it is addressing more effectively the factors inhibiting the
processing of remaining claims and reducing the claims
outstanding. Some of this has reflected the sheer size of
these schemes, for example the need for the Department’s
medical contractors to employ large numbers of specialist
staff which were not available in the numbers required.
The Department has sought to simplify some procedures.
Most notably, working with solicitors and the Court,
it took action to reduce the volume of outstanding
COPD claims, which had reached 400,000 in 2004, by
introducing a fast-track option in 2005, known as the
Optional Risk Offer Scheme. Some 170,000 claimants
have now chosen this option.
- The COPD scheme has been particularly costly to
administer. We estimate that, at 31 March 2007, around
69 per cent of all claimants paid compensation have
received less than the average cost of administering the
claims (£3,200 per claim up to March 2007). For the VWF
scheme the equivalent figure is around seven per cent.
The fast-track option for COPD, which the Department
developed from its experiences administering the scheme,
has helped to reduce both administrative costs and the
timescale for claim settlements.
- The Department’s approach to negotiating the
original fees tariffs with solicitors in 1999 was weak.
Whilst this was not a standard procurement matter where
the Department could select its suppliers, its preparation
lacked the depth of analysis that might ordinarily have
been expected to support its negotiations in a commercial
setting. The negotiations took place in the midst of
pressure to reach agreement, uncertainty over the likely
number of claims and the practicalities of operating the
schemes, yet the Department tied itself into an agreement
which made no provision for the tariff to be reviewed
in the light of experience. At the time, the Department
believed that the closure of the schemes to new claims
would happen within around two years. The Department
was therefore in a weak position once the assumptions
underpinning its initial analysis proved to be erroneous.
- An analysis prepared by a Cost Judge – in connection
with a recent challenge by the Department of costs payable
under the fast-track COPD scheme – has suggested that
the costs payable under the original tariff were in excess of
the levels that would be awarded following a conventional
detailed assessment based on data currently available. We
have calculated that, had costs payable to solicitors been in
line with the findings of the Cost Judge several years later,
the total amount payable by the Department to solicitors
would have been £295 million less. We are not suggesting
that the Department was able to negotiate an agreement
from the outset at the levels identified by the Cost Judge
as only limited information was available. This reinforces
the desirability of introducing a review clause in such
instances, although such a clause can work to the advantage
of either party. There are no comparable figures available
for VWF general damages[Footnote 5] claims. Drawing on lessons
learnt throughout the schemes, the Department is currently
negotiating the tariff to be paid for VWF services claims.
- Although still tied to the original agreements, the
Department has sought to negotiate down the costs
associated with subsequent changes to the schemes. It
contested, for example, the fees payable on the fast-track
COPD procedure because of the lower level of solicitor
input. The Court ruled in April 2007 that the fees for the
fast-track procedure should be set at levels lower than
those where a claim involves a full medical assessment.
The reduction in fees arising from this ruling is likely to
reduce the cost to the taxpayer by up to £100 million.
- The Department has set aspirational dates for the
effective completion of both schemes. A significant
proportion of the remaining claims, however, raise
complicated issues. The Department has mapped out the
risks it now faces, including the need to work effectively
with its contractors and solicitors, and has sought to put in
place arrangements to manage these issues. Closure of the
schemes will not, by itself, finally discharge all liabilities
and will not prevent future coal health related claims
being brought against the Department. The Department is
aware of these risks and applying its experience from the
COPD and VWF schemes in managing them.
