Project Control
Phase I Methodology
Phase 1 - Methodology
|
Phase 2 - Consultation and Fieldwork
|
Phase 3 - Project Control
|
Causal Maps
In early 2003, the National Audit Office began a series of work
on benchmarking the Ministry of Defence's acquisition system. The
aim of this work is to add value to the Ministry of Defence's
understanding of the key influences upon the acquisition system and
how these can best be managed to achieve timely and cost-effective
delivery of capability.
PA Consulting Ltd were commissioned to undertake some systems
dynamics based analysis of the MoD's acquisition system to identify
the key drivers of the performance of major defence projects.
This analysis was unique in looking from the outside at the
broader drivers bearing on the success of the MoD' s internal
processes, rather than at the processes themselves.
The NAO adopted an inclusive and incremental approach. Inclusive
in that the Ministry of Defence was closely involved at all stages
and incremental in that there were discrete steps to manage the
risks involved and ensure the utility of the outputs in terms of
improved acquisition of military capability.