Carrier Strike: The 2012 reversion decision

The Ministry of Defence acted quickly once it realized, in early 2012, the extent to which its 2010 decision to procure the carrier variant of the Joint Strike Fighter (JSF) had been based on immature data and flawed assumptions. In May 2012, the Department announced that it was reverting to procuring the short take-off and vertical landing (STOVL) variant of the fighter. In a report published today examining that 2012 decision, the National Audit Office has called for the Department to introduce a degree of consistency in decision-making not previously apparent in the Carrier Strike programme and to work within the financial and capability assumptions underpinning the decision, if it is to deliver value for money.

By February 2012, the estimated cost of converting the aircraft carrier for the carrier variant of the JSF, requiring the ship to be fitted with catapults and arrestor gear (‘cats and traps’), had increased by 150 per cent: from £800 million to about £2 billion.  As a result, the Department estimated that, over the next ten years, the STOVL option would be £1.2 billion cheaper than the carrier variant. This difference halves to £600 million over 30 years.

Another key factor was that the carrier variant option of the JSF could also not be delivered until 2023, three years later than the planned date of 2020. The Chief of Defence Staff judged that, in the emerging security environment, such a gap in capability would be undesirable. When the Department reverted to the STOVL option, it announced that it would deliver the Carrier Strike by 2020. However, a week later, it delayed investment in Crowsnest, the helicopter based radar system making up the third element of Carrier Strike, meaning that the system is not now scheduled to be fully operational until 2022, two years later than the carriers and aircraft.

Resolving the future of the Carrier Strike programme (comprising the Queen Elizabeth class aircraft carriers, the Joint Strike Fighter aircraft operating from them and Crowsnest) was central to the Department’s efforts to balance its ten-year equipment budget. When the implications of the 2010 decision became clear, the Department acted quickly to put in place a unique, streamlined approvals structure, with focused attention from senior officials. This was crucial to the pace of decision-making.

The Department expects to write off £74 million as a result of the reversion decision; but this cost could have been ten times higher if the decision had been made after May 2012.

Successful delivery will require the Department to manage significant affordability and technical risks. There are cost, schedule and technical risks across the JSF programme over which the Department has limited control. The highest risk phases of carrier construction and integration are yet to come and the Department must successfully conclude complicated negotiations with commercial partners.

Today’s report notes that the carrier variant of the JSF has a greater range and payload than the STOVL variant and would have provided a more effective strike capability. However, STOVL creates the option to operate Carrier Strike from two carriers, providing continuous capability. By contrast, the carrier variant could operate from only the one carrier installed with cats and traps and therefore could provide capability for only 70 per cent of the time.

“It is good that the MOD acted promptly, once it became clear that pursuing the option to buy the carrier variant aircraft would cost a lot more money and add another three years to the whole programme. But to achieve value for money in this project, the Department will have to manage significant technical and affordability risks and be consistent in sticking to the present plan.”

Amyas Morse, head of the National Audit Office

Notes for Editors

 

2020planned in-service date of Carrier Strike after both the 2010 and 2012 decisions £1.2bnDepartment's estimate of cost savings, over the next 10 years from the 2012 reversion decision 150 per centincrease in the Department's 'cats and traps' cost estimate, since the 2010 Strategic Defence and Security Review
£0.6 billion Department's estimate of cost savings, over the next 30 years from the 2012 reversion decision, a reduction from the savings estimated over the next 10 years - as a result of costs in years 10 to 30
£74 million departmental estimate of the write-off of spend as a result of the 2012 reversion decision
3 years delay (from 2020 to 2023) to the Department's planned Carrier Variant option delivery, arising between the 2010 and 2012 decisions
2 years delay (from 2018 to 2020) to the Department's planned STOVL option delivery, arising between the 2010 and 2012 decisions
2 years between the Department's planned STOVL option delivery (in 2020) and its current plans to deliver the third element of Carrier Strike – Crowsnest, a helicopter-based radar system (in 2022)
55 per cent increase in the Department's estimate to procure two aircraft carriers, between 2005 and 2012
100 per cent increase in the estimated cost of each Joint Strike Fighter aircraft, between 2001 and 2012

 

  1. Press notices and reports are available from the date of publication on the NAO website, which is at www.nao.org.uk. Hard copies can be obtained from The Stationery Office on 0845 702 3474.
    1. The NAO’s vision is to help the nation spend wisely. Its independent public audit perspective helps Parliament hold government to account and improve public services. The Comptroller and Auditor General (C&AG), Amyas Morse, is an Officer of the House of Commons and leads the NAO, which employs some 860 staff. The C&AG certifies the accounts of all government departments and many other public sector bodies. He has statutory authority to examine and report to Parliament on whether departments and the bodies they fund have used their resources efficiently, effectively, and with economy. Our studies evaluate the value for money of public spending, nationally and locally. Our recommendations and reports on good practice help government improve public services, and our work led to audited savings of more than £1 billion in 2011.