Investigation into devolved funding
Published on:This investigation covers how the UK government determines the amount of funding it allocates to the devolved administrations.
This investigation covers how the UK government determines the amount of funding it allocates to the devolved administrations.
In May 2012, the Department of Transport expected the tram-train scheme to be completed by Dec 2015. It is now expected to be completed in May 2018.
Our financial audit reports contain audit opinions on accounts across the public sector.
In June 2015, the Secretary of State for Transport announced that two large rail electrification schemes would be paused because the rail investment portfolio was costing more and taking longer.
The Whole of Government Accounts (WGA) are the very first audited set of accounts showing in one place the financial position of the whole public sector. However, the NAO considers that the picture is incomplete.
Sir John Bourn, Head of the National Audit Office, told Parliament today that although the Private Finance Initiative deal for the construction of the Channel Tunnel Rail Link was in many respects unique, the lessons to be learned from the project’s near collapse are not. The report makes three key points. In negotiating with the […]
The HS1 project has delivered a high performing line, which was subsequently sold in a well-managed way. But international passenger numbers are falling far short of forecasts and the project costs exceed the value of journey time saving benefits.
This investigation outlines the government’s strategy and objectives for managing land disposals and the progress of several key disposal programmes.
In March 2007 we were invited by the House of Lords Select Committee on Regulators to review the way that impact assessment is performed by five regulators: Ofcom; Ofgem; Ofwat; Postcomm; and the Office of Rail Regulation (ORR).
The National Audit Office has today published the findings from its investigation into the Department for Transport’s (the Department’s) progress in implementing the South East Flexible Ticketing Programme (the Programme). In January 2012, the Department set up the Programme to improve coordination, speed up delivery and increase take up of smart ticketing. The Department was […]
Provides information on how the Department for Transport is organising itself to support a successful exit from the EU.
On 15 January 2018, Carillion declared insolvency and the Official Receiver, an employee of the Insolvency Service, started to liquidate its assets and contracts. This report focuses on the role of the UK government in preparing for and managing the liquidation of Carillion.
The Comptroller and Auditor General, Amyas Morse, has today qualified the accounts of High Speed Two (HS2) Limited owing to its running a redundancy scheme at enhanced terms without the necessary approvals.
HS2 is a large, complex and ambitious programme which is facing cost and time pressures. The unrealistic timetable set for HS2 Ltd by the Department means they are not as ready to deliver as they hoped to be at this point.
The National Audit Office has today published independent reviews of value for money savings reported by the Department for Transport and the Home Office as part of their 2008-09 Annual Reports. The Department for Transport reported savings of £892 million, of which the NAO found that 43 per cent fairly represent realised cash savings, 22 […]
The Whole of Government Accounts provide a unique perspective owing to their reach and approach to measuring the government’s financial performance and position.
A third of major government projects due to deliver in the next five years are rated as in doubt or unachievable unless action is taken to improve delivery. Greater transparency on project performance is required.
The Strategic Rail Authority (and, subsequently, the Department for Transport) and Network Rail have successfully turned around the programme to modernise the West Coast Main Line. To date, Network Rail has delivered the new strategy for the line on time, achieving benefits for passengers, including shorter journey times and improved punctuality. Network Rail is likely […]