Investigation into the rescue of Carillion’s PFI hospital contracts
Published on:Carillion going into liquidation left two new hospitals unfinished. The projects will now be completed with public finance.
Carillion going into liquidation left two new hospitals unfinished. The projects will now be completed with public finance.
Lessons from the large body of experience of using PFI can be applied to improve other forms of procurement. Government should also do more to act as an ‘intelligent customer’ in the procurement and management of projects.
Explore the trends in capital expenditure and resourcing since 2010-11 and build a richer understanding of what they mean for different local authorities.
The National Audit Office reported today that there was limited assurance that the price of the three Tube PPPs was reasonable, and some uncertainty about the eventual price although any price revisions have to meet tests of economy and efficiency. The complexity of the PPPs resulted from the scale of the deals, innovative output specifications […]
The National Audit Office reported today that there was limited assurance that the price of the three Tube PPPs was reasonable, and some uncertainty about the eventual price although any price revisions have to meet tests of economy and efficiency. The complexity of the PPPs resulted from the scale of the deals, innovative output specifications […]
We have published this model to provide guidance to Departments on HMT’s and NAO’s expectations of how they should manage their programmes involving PPP and PFI projects.
This report provides information on managing PFI contracts when they end and considers whether government is preparing for expiry appropriately.
This report provides information on managing PFI contracts when they end and considers whether government is preparing for expiry appropriately.
The Ministry of Defence has introduced positive changes to how it manages its estate and has invested substantial resources to maintain and improve it. The MoD, however, accepts that it has more work to do to provide a sustainable estate of the right quality, the National Audit Office has today reported to Parliament. The MoD […]
Most (81%) public bodies involved in PFI projects believe that they are achieving satisfactory or better value for money from their PFI contracts according to a National Audit Office report presented to Parliament today, based on the first ever major survey of central government PFI projects in progress. There was generally positive feedback from service […]
This memorandum has been prepared to support the Environmental Audit Committee to consider the decision taken by Defra in 2010, to withdraw the provisional allocation of PFI credits from seven (out of 18) PFI projects.
The new military flying training is 6 years delayed and there is much to do if the MoD is to get the planned benefits from its contractor.
Sir John Bourn, Head of the NAO, told Parliament today that the Ministry of Defence (the MOD) is making progress towards delivering an Initial Operating Capability for the Apache helicopter in August 2004 but that risks remained. The MOD is buying 67 Apache helicopters through a £3 billion prime contract with Westland Helicopters Ltd. The […]
The National Audit Office has been unable to conclude that the Ministry of Defence has achieved value for money from the procurement phase of its £10.5 billion private finance deal for the Future Strategic Tanker Aircraft (FSTA), according to a report released today. Despite managing the later stages of the procurement well, the MOD’s ability […]
MOD expects to secure significant benefits as a result of letting a PFI contract for the redevelopment of its Head Office Main Building in Whitehall according to Sir John Bourn, Head of the National Audit Office in a report presented to Parliament today. As a result of letting a 30 year PFI contract with a […]
Sir John Bourn, Head of the National Audit Office, told Parliament today that the Joint Services Command and Staff College was a success story and had obtained value for money when using the PFI to procure its permanent home. The Ministry of Defence did well to establish the College but there is scope to improve […]
Last updated – 28 May 2020 Introduction to the topic This online publication provides results of a survey we conducted with public sector authorities (authorities) and which forms part of the evidence base of the NAO’s report on Managing PFI assets and services as contracts end. This report provides information on how public authorities manage […]
A national standard IT system for magistrates’ courts has been under development for over ten years but is still not complete, Sir John Bourn, head of the National Audit Office, reported to Parliament today. The cost of the project has increased substantially since a PFI deal was signed in 1998. IT systems in magistrates’ courts […]
Sir John Bourn, head of the National Audit Office, reported to Parliament today on the Summarised Accounts of the National Health Service in Scotland for 1998-99. The report describes the findings of the appointed auditors of the individual health bodies, discusses developments in accounting and financial control, considers the financial performance of the NHS in […]